Gents: I just got the actual totals to date – see correction below and let me know what you guys want to do. Thanks, Eric Little Project Manager, UDR 5430 LBJ Freeway, Suite 1250 Dallas, TX 75240 Ph: 972.774.0552 Fx: 972.991.4113 Cell: 214.641.5761 www.UDR.com From: Eric T. Little Sent: Thursday, June 24, 2010 1:54 PM To: 'Bruce Dunne'; Clay Barnett Subject: RE: Change Order # 3 - Park Package I don’t see any issues with this CO. I did speak to Zach a few minutes ago and he stated that we are over on the casing quantity already. Below is where we are now, this will go up. CONTRACT ACTUAL TO DATE Item # Description/Work Qty Unit Unit Price Amount Qty Unit Unit Price Amount 321 12" DIA PIER CASING (IF REQ'D) 250 VF $ 40.00 $10,000.00 822 VF $ 40.00 $32,880 The 850VF is approx right now, I’m awaiting the final numbers. They are wanting to add this to the CO 3 if possible. If you guys want to do that, then we will have to wait until I get the final numbers from NTC. Otherwise, everything else on this CO is good to go as far as I can tell. Thanks, Eric Little Project Manager, UDR 5430 LBJ Freeway, Suite 1250 Dallas, TX 75240 Ph: 972.774.0552 Fx: 972.991.4113 Cell: 214.641.5761 www.UDR.com From: Bruce Dunne [mailto:bdunne@icon-engineers.com] Sent: Wednesday, June 16, 2010 8:51 PM To: Clay Barnett Cc: Eric T. Little Subject: Change Order # 3 - Park Package Attached is Change Order # 3 for the Park Package. Please review and give me your thoughts so I can finish up. Thanks. BRUCE F. DUNNE, P.E. President icon Consulting Engineers, Inc. Bicentennial Financial Center 250 W. Southlake Blvd., Suite 117 Southlake, Texas 76092 Phone: (817) 552-6210 Fax: (817) 552-3126 Mobile: (817) 707-9711