Bruce, Two comments: 1. Items CO4-10 & CO4-11 I believe are reversed. CO4-10 should be 153 and CO4-11 should be 152. Please switch and re-label them. Also, if you could make them each so that they tie to the original item that would be helpful. 2. I added the numbers and do not get $264,829.05. Could you check it? Please make the corrections. I would like a copy in word as well. Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857 From: Bruce Dunne [mailto:bdunne@icon-engineers.com] Sent: Friday, October 22, 2010 8:04 AM To: Clay Barnett Cc: Eric T. Little; zfusilier@ntexcon.com Subject: Change Order #4 See attached change order #4 per our meeting yesterday. BRUCE F. DUNNE, P.E. President icon Consulting Engineers, Inc. Bicentennial Financial Center 250 W. Southlake Blvd., Suite 117 Southlake, Texas 76092 Phone: (817) 552-6210 Fax: (817) 552-3126 Mobile: (817) 707-9711