Thanks Clay. Appreciate you looking into this for us. From: Clay Barnett [mailto:cbarnett@addisontx.gov] Sent: Tuesday, August 30, 2011 2:56 PM To: Bruce Dunne Cc: Nick Jacob (PJacob@udr.com) Subject: Contract Start Date Bruce, They were released for construction on April 29, 2010. I have attached the preconstruction agenda for your reference. The original contract time was 590 days. Additionally, we added 35 days with Change Order #4 and 5 days with Change Order #5. This would place the completion date at 12/10/2011. If you recall, there was only $50,000 worth of incentive in the original bid. NTC told us that they would forego that amount in lieu of a private agreement with UDR. I have not seen that agreement so I do not know what it entails. Also, the wording in the Town’s contract is incorrect and may not be enforceable. If you have any questions, please let me know. Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857