Hattie, Below is the cost breakdown for the park: Category Cost Site Prep, Erosion Control & Dewatering $ 1,086,466 Earthwork & Grading $ 1,150,589 Trails & Railings $ 648,284 Retaining & Screening Walls $ 1,304,744 Utilities $ 420,820 Electric & Site Lighting $ 784,508 Park Signage & Furniture $ 153,500 Landscaping $ 551,116 Irrigation $ 213,751 Misc $ 1,105,510 Amphitheater $ 117,092 Grotto Fountain $ 842,712 Wildlife Observation Deck $ 313,385 Belvedere $ 68,160 Street $ 78,932 Duct Bank $ 45,290 “Misc” includes the fords, weirs, water recirculation system, stone veneer on the bridge abutments and decretive granite bollards. I can break any and all of those out as needed. I will request the contractor’s schedule for the park construction. Please let me know if there is anything that I am missing. Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857 From: Peterson, Hattie [mailto:hpeterson@Halff.com] Sent: Friday, October 08, 2010 4:42 PM To: Nancy Cline; Slade Strickland; Clay Barnett Cc: Witte, Mark Subject: Phase II NCTCOG Grant Attached is the II presentations. A few minor things still needed. Phase II 1. Mark will add map of Redding Trail Construction Infrastructure (Mark Witte) 2. Need Detailed costs for Construction project. For STREET CONSTRUCTION; BIKE/PEDESTRIAN TRAIL; INTERSECTION; SIGNALIZATION; DUCT BANK; UTILITES; LIGHTING; RETAINING WALLS, ETC (Clay) 3. Detailed schedule for construction (Clay) 4. Need detailed costs for Pedestrian and landscaping (SIDEWALKS, STREETLIGHTS, LANDSCAPING) (Clay) I do need to get on the road, but will be taking this with me, so please feel free to email me the information or call me on my cell phone at 469.939.3783. Thank you. Hattie Hattie Peterson Director of Marketing HALFF ASSOCIATES, INC. 1201 North Bowser Road Richardson, Texas 75081 Phone 214-346-6200 Fax 214-739-0095 www.halff.com