Clay, Per our discussion we are moving in a double drum walk behind compactor and will dedicate the entire day tomorrow to proof rolling all areas except those that are shale. We will also clean the dirt that was stock piled to handle the storm sewer at the weir located under Ponte tomorrow. After this we will release water and remove pumps. We will take photo's of the removed dirt as well as be submitting an asbuilt survey from a RPLS by the end of the week that certifies and shows that we are completely within elevation tolerance. Thanks again. Zach Fusilier North Texas Contracting Office - 817-430-9500 Cell - 817-819-6691 Email - zach@ntexcon.com From: Clay Barnett [mailto:cbarnett@addisontx.gov] Sent: Wednesday, August 24, 2011 3:25 PM To: 'Zach' Subject: FW: Reach 2 & 3 punch pictures Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857 From: Nick Jacob [mailto:PJacob@udr.com] Sent: Wednesday, August 24, 2011 2:44 PM To: Clay Barnett Subject: Reach 2 & 3 punch pictures Clay, Attached are the pictures regarding the loose soils on the shelf within reach 2 & 3. Let me know if you would like any additional pictures. Thanks, Nick