The well construction period is estimated at 120 days. Additional time will be required for the construction of a CMU pump house once the well is complete. The current schedule calls
for Kleinfelder to have final plans and specs on June 24th. At the kick off meeting Nancy mentioned your advertisement period is 6 weeks. If we advertise the last week of June and
open bids mid-August the well construction should be complete by mid-November.
Hope that answers your question. I can give you a better estimate for the pump house construction once I spec the equipment.
Lisa Larson
Project Engineer
Kleinfelder
1826 Kramer Lane, Suite M
Austin, TX 78758
o| 512.926.6650
d| 512.491.4606
c| 512.947.3245
f | 512.833.5058
From: Clay Barnett [mailto:cbarnett@addisontx.gov]
Sent: Wednesday, May 11, 2011 1:56 PM
To: Lisa Larson
Subject: FW: Schematic Drawing
Lisa,
I asked Eric to plug this into the schedule. Could you give me an estimate on when the driller would be out there and approximate duration based upon the current schedule?
Thanks,
Clay Barnett, P.E.
Town Engineer
Town of Addison
16801 Westgrove Drive
Addison, TX 75001-2818
Office: (972) 450-2857
From: Eric T. Little [mailto:ELittle@udr.com]
Sent: Wednesday, May 11, 2011 1:54 PM
To: Clay Barnett
Cc: Nick Jacob
Subject: RE: Schematic Drawing
I’m sure we can. It would be helpful to know how long the driller will be in the area……..will affect the tree planting and irrigation over there which I don’t have a drawing of.
Let’s talk about it at tomorrows meeting…
Thanks,
Eric
From: Clay Barnett [mailto:cbarnett@addisontx.gov]
Sent: Wednesday, May 11, 2011 1:51 PM
To: Eric T. Little
Cc: Nick Jacob
Subject: RE: Schematic Drawing
Can we move some stuff around?
Clay Barnett, P.E.
Town Engineer
Town of Addison
16801 Westgrove Drive
Addison, TX 75001-2818
Office: (972) 450-2857
From: Eric T. Little [mailto:ELittle@udr.com]
Sent: Wednesday, May 11, 2011 1:50 PM
To: Clay Barnett
Cc: Nick Jacob
Subject: RE: Schematic Drawing
The paving on Bella is supposed to go from 7/5 to 8/3. That being said, putting this staging here here screws things up not only for Bella, but for our tree farm that is supposed to
be done before the big shindig in August……..
From: Clay Barnett [mailto:cbarnett@addisontx.gov]
Sent: Wednesday, May 11, 2011 1:45 PM
To: Eric T. Little
Cc: Nick Jacob
Subject: FW: Schematic Drawing
Eric,
Could you put this on the schedule and let me know how badly it screws things up?
Thanks,
Clay Barnett, P.E.
Town Engineer
Town of Addison
16801 Westgrove Drive
Addison, TX 75001-2818
Office: (972) 450-2857
From: Lisa Larson [mailto:LLarson@kleinfelder.com]
Sent: Wednesday, May 11, 2011 11:18 AM
To: Clay Barnett
Subject: Fw: Schematic Drawing
Clay,
Per our phone conversation we wanted to make you aware of a schedule conflict between the well construction and Bella Lane paving. I've attached a schematic showing the minimum construction
staging area for the well. The project schedule shows paving for Bella Lane in July. Any finished paving would likely be damaged during the well construction.
Lisa
--------------------------
Sent using BlackBerry
________________________________
From: Gary Witt
To: Lisa Larson
Sent: Wed May 11 06:51:40 2011
Subject: Schematic Drawing
Please See Attached
G.(Witt) Witterstaetter
Technician II
1826 Kramer Lane, Suite M
Austin, Texas 78758
o| 512.926.6650
d| 512.491.4615
f | 512.833.5058
******************************************************************************************************************
This e-mail and any files or attachments transmitted with it contains Information that is confidential and privileged. This document may contain Protected Health Information (PHI) or
other information that is intended only for the use of the individual(s) and entity(ies) to whom it is addressed. If you are the intended recipient, further disclosures are prohibited
without proper authorization. If you are not the intended recipient, any disclosure, copying, printing, or use of this information is strictly prohibited and possibly a violation of
federal or state law and regulations. If you have received this information in error, please delete it and notify Hamid Khaleghipour at 972-450-2868 immediately. Thank you.
*******************************************************************************************************************
******************************************************************************************************************
This e-mail and any files or attachments transmitted with it contains Information that is confidential and privileged. This document may contain Protected Health Information (PHI) or
other information that is intended only for the use of the individual(s) and entity(ies) to whom it is addressed. If you are the intended recipient, further disclosures are prohibited
without proper authorization. If you are not the intended recipient, any disclosure, copying, printing, or use of this information is strictly prohibited and possibly a violation of
federal or state law and regulations. If you have received this information in error, please delete it and notify Hamid Khaleghipour at 972-450-2868 immediately. Thank you.
*******************************************************************************************************************