10-4 – I forgot to do that. Thanks Joel. Here is the updated version. Let me know if you guys see any other issues. Thanks, Eric From: Joel Massey [mailto:jmassey@icon-engineers.com] Sent: Friday, May 27, 2011 8:50 AM To: Eric T. Little Cc: Jennifer Haynes; Nick Jacob; wgeistweidt@kleinfelder.com; zackf; Barnett, Clay Subject: RE: Vit Park - Phase 1C - CO 6 Status Eric, Item 41 should be removed from CO6. It was already included in CO4 (items 40 & 41). Joel A. Massey Project Manager icon Consulting Engineers, Inc. Bicentennial Financial Center 250 W. Southlake Blvd., Suite 117 Southlake, Texas 76092 Phone: (817) 552-6210 Fax: (817) 552-3126 Mobile: (817) 229-7944 jmassey@icon-engineers.com From: Eric T. Little [mailto:ELittle@udr.com] Sent: Friday, May 27, 2011 8:41 AM To: zackf; Joel Massey; Barnett, Clay Cc: Jennifer Haynes; Nick Jacob; 'wgeistweidt@kleinfelder.com' Subject: Vit Park - Phase 1C - CO 6 Status All, Here is the current status of CO 6. We are down to the following items now: 1. Pending Kleinfelder review of Items 321 and 324 vs the pier logs. 2. NTC pricing on CO6-11 3. NTC review of UDR comments on pricing for granite bollards and Bilco hatch. 4. ICON removal of paving south of Ponte. Thanks, Eric