Thanks! The revised sheet is attached. (I’ve corrected some pier items that I had in there twice). From: Robyn Jacobson [mailto:rdj@kevinsloanstudio.com] Sent: Wednesday, May 18, 2011 2:56 PM To: Eric T. Little; Zach Fusilier; Jennifer Haynes; Joel Massey Cc: Nick Jacob; Tom Lamberth; Clay Barnett Subject: RE: Vit Park - Phase 1C - CO 6 Status According to our files, the center of the wall measures 84’-9 13/16. If you use the wildlife observation deck rail design which has 4’-0” bays this would be a 21 bay rail or 84’-0” with approximately 5” left over on each end of the wall. The guard should be mounted in the center of the cap and installation should begin at the center if possible. Let me know if you need additional information. ________________________________ From: Eric T. Little [mailto:ELittle@udr.com] Sent: Monday, May 16, 2011 2:58 PM To: Zach Fusilier; 'Jennifer Haynes'; 'Joel Massey'; Robyn Jacobson Cc: Nick Jacob; Tom Lamberth; 'Clay Barnett' Subject: Vit Park - Phase 1C - CO 6 Status All, Here is where we are at on CO #6. ICON – Need you guys to verify the quantity on the 4” thick sidewalk that connects the ped bridge to the Savoye sidewalk by the dog run. KSS – Need you guys to verify the quantity on the rail at the Tree Protection Rail. NTC – Need you guys to verify the quantity on the stone veneer, the 12” piers, the soil nail walls and provide a price on the paver removal/reset. Thanks, Eric