Bruce, On Change Order #2, several items are in the base bid. If they are in the base bid, we cannot use the CO2-#m, we have to use the BID-#. Please call me when you get a chance so that we can discuss this. Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857 From: Bruce Dunne [mailto:bdunne@icon-engineers.com] Sent: Tuesday, May 11, 2010 5:15 PM To: Zach Fusilier Cc: Clay Barnett; Eric T. Little Subject: FW: Vitruvian Park - Change Order # 2 for Park Package Zach - Attached is the revised Change Order # 2 to the Park contract. It includes the Ponte Avenue construction that was deleted from Phase 1B, the demolition items related to the existing box culverts on Ponte Avenue, and the demolition of the existing bridge just downstream of future Bella Lane. Please review and give me your comments on this. Thanks. BRUCE F. DUNNE, P.E. President icon Consulting Engineers, Inc. Bicentennial Financial Center 250 W. Southlake Blvd., Suite 117 Southlake, Texas 76092 Phone: (817) 552-6210 Fax: (817) 552-3126 Mobile: (817) 707-9711