Bruce: NTC is saying the piers are off on the CO6. I can’t figure out where the heck we are on these two items: Item 324 (which really should be under CO1-20) had: 4275 vf in CO1 450 vf in CO4 4725 vf TOTAL Installed to date = 5326 vf Add to change order 601 vf Item 329 1420 vf in Original Contract 349 vf in CO4 1769 vf TOTAL Installed to date = 2206 vf Add to change order 437 vf Please take a look and let me know what you guys think. Eric From: Eric T. Little Sent: Wednesday, July 13, 2011 9:16 AM To: 'Clay Barnett'; 'Bruce Dunne' Cc: 'Joel Massey'; Tom Lamberth Subject: RE: Vitruvian Park - Change Order #6 Bruce, Don’t add the low water crossing. NTC has already been paid for this work by UDR. I need to get with Clay on the reimbursement to UDR. Thanks, Eric From: Eric T. Little Sent: Wednesday, July 13, 2011 9:02 AM To: 'Clay Barnett'; 'Bruce Dunne' Cc: Joel Massey; Tom Lamberth Subject: RE: Vitruvian Park - Change Order #6 Bruce, Here are my final changes to this Change Order: Add the following items: #122 Elec Conductor No. 0 CU Insul – 40lf X 2.00 #131 Elec Serv to Pan GA in 3” SCH 40 Cond – 169lf X 25.00 CO6-7 Tree and Mulch Haul Off – Increase quantity to 50ea. CO6-12 – 796lf 4/0 CO6-13 – Additional BMPs For USACE (Split with Contractor) – 1LS X $28,982 (We agreed with NTC to split the cost off all the BMPs above and beyond what was required in the plan) CO6-14 – Low Water Crossing Split Cost – 1LS X $8,862 (UDR has paid the other half already). Let me know if you guys have any questions. Thanks, Eric From: Clay Barnett [mailto:cbarnett@addisontx.gov] Sent: Monday, June 27, 2011 4:53 PM To: Eric T. Little Cc: Joel Massey; 'Bruce Dunne' Subject: RE: Vitruvian Park - Change Order #6 Eric, The Change Order looks good with the exception of the missing price. Please be aware that the following items that have been paid for will be reduced: Item 112 – 260lf Item CO1-2 – 150lf Item CO1-20 – 1559vf Item CO2-19 – 33lf Item CO2-30 – 85lf Item CO2-38 – 110lf Please confirm that these are correct. These would reduce the June pay application (Pay Application 15) by $73,191.22. Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857 From: Bruce Dunne [mailto:bdunne@icon-engineers.com] Sent: Monday, June 27, 2011 8:22 AM To: Clay Barnett Cc: Eric T. Little; Joel Massey Subject: Vitruvian Park - Change Order #6 Attached is the revised version of Change Order No. 6. It is still missing the length of wire (Item CO6-12). Let me know if there is anything else you would like to change. BRUCE F. DUNNE, P.E. President icon Consulting Engineers, Inc. Bicentennial Financial Center 250 W. Southlake Blvd., Suite 117 Southlake, Texas 76092 Phone: (817) 552-6210 Fax: (817) 552-3126 Mobile: (817) 707-9711 ************************************************************ This e-mail and any files or attachments transmitted with it contain Information that is confidential and privileged. This document may contain Protected Health Information (PHI) or other information that is intended only for the use of the individual(s) and entity(ies) to whom it is addressed. If you are the intended recipient, further disclosures are prohibited without proper authorization. If you are not the intended recipient, any disclosure, copying, printing, or use of this information is strictly prohibited and possibly a violation of federal or state law and regulations. If you have received this information in error, please delete it and notify Hamid Khaleghipour at 972-450-2868 immediately. Thank you. ************************************************************