Ok. Once we get it, I’ll forward over to Zach to review and comment. Thanks, From: Joel Massey [mailto:jmassey@icon-engineers.com] Sent: Thursday, June 16, 2011 2:05 PM To: Eric T. Little Cc: Clay Barnett; Zach Fusilier; jennifer@ntexcon.com; Nick Jacob; Tom Lamberth; Bruce Dunne Subject: RE: Vitruvian Park - Phase 1C - Change Order #6 Final Pricing Eric, The new price provided for the OOOO copper electric conductor is too high. In lieu of adding this new item, we have included bid item 131, F & I Electric Service to Panel GA, and added an additional 169 LF at $25.00/LF. We are adding the latest additional items that you provided and will send you the CO #6 very soon. Joel From: Eric T. Little [mailto:ELittle@udr.com] Sent: Wednesday, June 08, 2011 10:43 AM To: Joel Massey Cc: Clay Barnett; Zach Fusilier; jennifer@ntexcon.com; Nick Jacob; Tom Lamberth; Bruce Dunne Subject: RE: Vitruvian Park - Phase 1C - Change Order #6 Final Pricing Gauntt tells me that the price of copper is up significantly since the project was bid in 2008. That’s why the new wire price is higher. Thanks, Eric From: Joel Massey [mailto:jmassey@icon-engineers.com] Sent: Wednesday, June 08, 2011 7:51 AM To: Eric T. Little Cc: Clay Barnett; Zach Fusilier; jennifer@ntexcon.com; Nick Jacob; Tom Lamberth; Bruce Dunne Subject: RE: Vitruvian Park - Phase 1C - Change Order #6 Final Pricing Eric, I will get you the information for the Ponte paving removal. It looks like we will have to add some concrete pavement also because the original quantity was based on the old bridge design which was longer. The new bridge is shorter and additional concrete pavement will be required. The price shown for the OOOO Electric Conductor is over 3 times the cost of the LARGER 250 MCM conductor. Joel A. Massey Project Manager icon Consulting Engineers, Inc. Bicentennial Financial Center 250 W. Southlake Blvd., Suite 117 Southlake, Texas 76092 Phone: (817) 552-6210 Fax: (817) 552-3126 Mobile: (817) 229-7944 jmassey@icon-engineers.com From: Eric T. Little [mailto:ELittle@udr.com] Sent: Tuesday, June 07, 2011 4:46 PM To: Joel Massey Cc: Clay Barnett; Zach Fusilier; Jennifer Haynes (jennifer@ntexcon.com); Nick Jacob; Tom Lamberth Subject: Vitruvian Park - Phase 1C - Change Order #6 Final Pricing Joel, Here is my final run through on CO #6 and all the associated back-up. Three notes here: 1. ICON needs to add in the credit for the deleted paving south of Ponte. 2. The Bilco Hatch issue seems like it’s going away. 3. The granite bollards pricing might need to go away if we just go back to the original design. Let me know if you have any questions. Thanks, Eric