Clay – This looks good to go. Thanks, Eric From: Bruce Dunne [mailto:bdunne@icon-engineers.com] Sent: Wednesday, February 16, 2011 10:04 AM To: Eric T. Little Cc: cbarnett@addisontx.gov Subject: RE: Vitruvian Park - Phase "1C" Change Order #5 Here you go. From: Eric T. Little [mailto:ELittle@udr.com] Sent: Wednesday, February 16, 2011 9:56 AM To: Bruce Dunne Cc: cbarnett@addisontx.gov Subject: RE: Vitruvian Park - Phase "1C" Change Order #5 Sorry, you’re right. The wording is wrong on the pay app, not on your change order. I’ll get that fixed. So it appears that #112 is good to go, if you could just fix #329, the CO should be good to go. From: Bruce Dunne [mailto:bdunne@icon-engineers.com] Sent: Wednesday, February 16, 2011 9:28 AM To: Eric T. Little Cc: cbarnett@addisontx.gov Subject: RE: Vitruvian Park - Phase "1C" Change Order #5 On my copies of Change Order #4 and Change Order #5, I show the exact same description for pay item 112, “Furnish & Install Irrigation Conduits”. Regarding the quantity for item #112, we added 59 feet on sheet C801, we added 54 feet to sheet C802 and we added 160 feet to sheet C803 for a total add of 273 feet. I then deducted 206 feet that was changed from 1-6” and 1-2” conduit to 1-8” and 1-2” conduit, thus resulting in a total add of 67 feet for the bid item #112, 1-6” and 1-2” conduits. From: Eric T. Little [mailto:ELittle@udr.com] Sent: Wednesday, February 16, 2011 8:51 AM To: Bruce Dunne Cc: cbarnett@addisontx.gov Subject: RE: Vitruvian Park - Phase "1C" Change Order #5 Well, can we use the same descriptions on each change order? It’s very confusing the way we’re doing it now. Also, on the draft CO5 you sent me, Item #112 was increased 209lf, but on the one you sent yesterday it was only increased 67lf – so once we remove the 206lf that’s being replaced by the 8” sleeves, I’m not sure if that leaves the revised quantity for #112 at 714lf or 856lf…..can you check that please? Thanks, From: Bruce Dunne [mailto:bdunne@icon-engineers.com] Sent: Wednesday, February 16, 2011 8:44 AM To: Eric T. Little Subject: RE: Vitruvian Park - Phase "1C" Change Order #5 The original bid item descriptions are too long to fit on a single line item in the change orders and thus have been abbreviated. From: Eric T. Little [mailto:ELittle@udr.com] Sent: Wednesday, February 16, 2011 7:48 AM To: Bruce Dunne; cbarnett@addisontx.gov Subject: RE: Vitruvian Park - Phase "1C" Change Order #5 Bruce, On #112 the original description was “1-6” & 1-2” SCH 40 PVC IRR CONDUITS”, however on CO #4 you changed it to “IRRIGATION CONDUITS” and now on this one its “FURNISH & INSTALL IRRIGATION CONDUITS”…….. For the sake of clarity, can we please use the same descriptions for the change orders that were originally used in the bid docs? This seems to be an issue on almost every single item and I’m not sure why we’re changing the descriptions…………if there’s a reason, please let me know, otherwise can you correct this please? Thanks, Eric From: Eric T. Little Sent: Tuesday, February 15, 2011 4:58 PM To: 'Bruce Dunne'; 'cbarnett@addisontx.gov' Subject: RE: Vitruvian Park - Phase "1C" Change Order #5 Clay, I forgot to attach this email. This explains the pier depth change. Thanks, Eric From: Eric T. Little Sent: Tuesday, February 15, 2011 4:49 PM To: 'Bruce Dunne'; 'cbarnett@addisontx.gov' Subject: RE: Vitruvian Park - Phase "1C" Change Order #5 Clay, Here is the email that explains the two changes below. Thanks, Eric From: Eric T. Little Sent: Tuesday, February 15, 2011 4:44 PM To: 'Bruce Dunne'; 'cbarnett@addisontx.gov' Subject: RE: Vitruvian Park - Phase "1C" Change Order #5 And change #329 to 349.35lf. From: Eric T. Little Sent: Tuesday, February 15, 2011 4:43 PM To: 'Bruce Dunne'; cbarnett@addisontx.gov Subject: RE: Vitruvian Park - Phase "1C" Change Order #5 You need to deduct 206lf from pay item #112. From: Bruce Dunne [mailto:bdunne@icon-engineers.com] Sent: Tuesday, February 15, 2011 4:26 PM To: cbarnett@addisontx.gov Cc: Eric T. Little Subject: Vitruvian Park - Phase "1C" Change Order #5 See attached change order for your review and comment. BRUCE F. DUNNE, P.E. President icon Consulting Engineers, Inc. Bicentennial Financial Center 250 W. Southlake Blvd., Suite 117 Southlake, Texas 76092 Phone: (817) 552-6210 Fax: (817) 552-3126 Mobile: (817) 707-9711