Zach, The $150,000 is a contingency for change orders. We cannot spend more than council authorizes, so this gives us a $150k ceiling for additional work before we have to go to council. If you have any additional questions, please let me know. Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857 -----Original Message----- From: Zach Fusilier [mailto:zfusilier@ntexcon.com] Sent: Saturday, February 20, 2010 12:28 PM To: 'Bruce Dunne' Cc: Clay Barnett Subject: RE: Vitruvian Park Change Order #1 Bruce / Clay, Not sure if this is a big deal, but the amount of Change Order # 1’s contract amount after the credit does not match the amount the City’s contract shows. The contracts I received from Finance show an amount of $ 8,611,131.54 which is $ 150,000 more than the contract shown on the change order. None of the alternates match the difference either. Can you help me figure it out. Thanks Zach Fusilier North Texas Contracting 4999 Keller Haslet Road Keller, Texas 76248 Office - 817-430-9500 Cell - 817-819-6691