Contract updated and bonding information attached. Matthew E. McCombs Management Analyst Town of Addison (972) 450-7090 Fax: (972) 450-7065 mmccombs@addisontx.gov -----Original Message----- From: Clay Barnett Sent: Monday, February 22, 2010 8:48 AM To: Matt McCombs Cc: 'Bruce Dunne'; 'Zach Fusilier' Subject: RE: Vitruvian Park Change Order #1 Matt, Please resend the contracts to North Texas Contracting, Inc. for $150k less than the amount awarded by council. We included the $150k for possible change orders. As the change orders occur Public Works will authorize the additional funds up to $150k. If you have any questions, please let me know. Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857 -----Original Message----- From: Clay Barnett Sent: Monday, February 22, 2010 8:38 AM To: 'Zach Fusilier' Cc: 'Bruce Dunne' Subject: RE: Vitruvian Park Change Order #1 Zach, The $150,000 is a contingency for change orders. We cannot spend more than council authorizes, so this gives us a $150k ceiling for additional work before we have to go to council. If you have any additional questions, please let me know. Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857 -----Original Message----- From: Zach Fusilier [mailto:zfusilier@ntexcon.com] Sent: Saturday, February 20, 2010 12:28 PM To: 'Bruce Dunne' Cc: Clay Barnett Subject: RE: Vitruvian Park Change Order #1 Bruce / Clay, Not sure if this is a big deal, but the amount of Change Order # 1’s contract amount after the credit does not match the amount the City’s contract shows. The contracts I received from Finance show an amount of $ 8,611,131.54 which is $ 150,000 more than the contract shown on the change order. None of the alternates match the difference either. Can you help me figure it out. Thanks Zach Fusilier North Texas Contracting 4999 Keller Haslet Road Keller, Texas 76248 Office - 817-430-9500 Cell - 817-819-6691