Zach, Please proceed with sending the submittals. As far as a start date, we are still working with Dallas County on the funding. We hope to have it wrapped up very soon. At any rate the signed contracts should allow North Texas to proceed with ordering materials, but we cannot proceed with construction until the funding agreement is in place with Dallas County. If you have any questions, please let me know. Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857 -----Original Message----- From: Zach Fusilier [mailto:zfusilier@ntexcon.com] Sent: Monday, March 15, 2010 10:27 AM To: Matt McCombs Cc: Clay Barnett Subject: Vitruvian Parl Matt / Clay, I was wondering the status of the signed contract so we can get a feel for a possible start date. The project team is planning and trying to put together the schedule. Thanks again. Can I start sending submittals in for items with long lead times? Zach Fusilier North Texas Contracting 4999 Keller Haslet Road Keller, Texas 76248 Office - 817-430-9500 Cell - 817-819-6691