Zach: Here are my notes on the CO 5 pricing items. 1. Lake Boulders – re-price showing RCP and the block once Jennifer and I work out exactly what we are going to do. 2. Added weir walls – I agree with your pricing – ICON is to include the credit for the walls already in the contract. 3. Cabinet Upgrade – ICON to review. 4. Steelco (Trellis) – I have several issues with this, please see my notes. 5. Trench Drain – change to galv finish and re-price. 6. Landscaping changes – ICON states that they have included the Reach 1 changes. They need to include the trees and irrigation at the former head-in parking location (colored in red on the attached spreadsheet). Everything else should be good to go. We need responses and finalization tomorrow – otherwise everything not finalized will be pulled off and put on CO 6. Thanks, Eric