Clay – per your request, attached is our Change in Scope and Fee request for additional services performed for the Vitruvian project. Also attached is a detailed breakdown including the description of the service provided and the associated cost for that service. I will also send you a hard copy of these documents via the mail. This CFS is all inclusive for services provided through September 10th. On another matter, at this time we are currently in week 80 of construction phase services. Our original proposal included 78 weeks of construction phase services. Assuming another 10 months of construction to complete the park package, this would mean adding an additional 43 more weeks of construction phase services. Assuming an average of 12 hours per week is spent on construction phase services, an additional $70,000 is anticipated to be required to complete the project. As we previously discussed, our allotted fee for Reimbursibles will not be reached. In fact, we should have right around $70,000 left over upon completion of the project. If this reimbursable allocation can be used for the additional construction phase services over the next 43 weeks, then it may not be necessary to request additional funding beyond this CSF #5. Thanks for your consideration. BRUCE F. DUNNE, P.E. President icon Consulting Engineers, Inc. Bicentennial Financial Center 250 W. Southlake Blvd., Suite 117 Southlake, Texas 76092 Phone: (817) 552-6210 Fax: (817) 552-3126 Mobile: (817) 707-9711