Stan, Here is a copy of the rain event report from the rain we got on Friday, Monday evening and early Tuesday morning. We are currently finishing up excavation, storm headwall and soil nail wall cap in Reach 3 (all the soil nail walls are complete) and we were pumping Reach 2 until the filtration basin was overwhelmed in Reach 1. The filtration basin is being repaired and we are building a larger cofferdam just south of the Ponte Bridge location to help better isolate Reach 2 from the creek flow in Reach 1. Please let me know if you have any questions or concerns. Thanks, Eric Little Project Manager, UDR 5430 LBJ Freeway, Suite 1250 Dallas, TX 75240 Ph: 972.774.0552 Fx: 972.991.4113 Cell: 214.641.5761 www.UDR.com