Stan/Bismarck: Attached is the report of the current status of the project. We experienced on Monday and Tuesday of this week (see Rain Event Report sent 11/17/2010). There is a chance of rain mostly on Monday and Wednesday of next week. As always, we will continue to monitor the weather and respond as needed and necessary. Let me know if you have any questions or concerns. Thanks, Eric Little Project Manager, UDR 5430 LBJ Freeway, Suite 1250 Dallas, TX 75240 Ph: 972.774.0552 Fx: 972.991.4113 Cell: 214.641.5761 www.UDR.com