Meeting Minutes For "Construction Meetings" Meeting No. 9 As of 22-Jul-2010 8:22 AM CT Vitruvian Infrastructure Phase 1C Park 4010 Marsh Lane Addison, Texas 75001 Project Number: 1308C Published Date/Place 15-Jul-2010 9:00 AM CT at Construction Trailer Prepared By Eric Little Attendees Clay Barnett Deiadra Burns Derek Dodson Wade Geistweidt Andrew Harper Jennifer Haynes Todd Henson Brian LaFoy Ron Lee Other Attendees tlamberth@udr.com Statement Next Meeting 22-Jul-2010 9:00 AM CT at (place to be determined) Old Business Topic 1.1 Mitigation Requirements In Progress -- Due Now Meeting Date: 6-May-2010 9:00 AM CT Click to view comments There has been some discussion on site with ToA about the mitigation plan and what trees stay and go. This needs to be settled today if possible. We all need to understand what we can and cannot do under the 404 permit and the mitigation plan. Status: In Progress Assigned To: Clay Barnett Brian LaFoy Eric Little Cy Reichert Due Date: 6-May-2010 5:00 PM CT Meeting Date: 13-May-2010 9:00 AM CT Discuss issues with NDM letter discussing ICON's calculations on the n value and the removal of existing vegetation for the park work. Status: In Progress Assigned To: (none) Due Date: - TBA - Meeting Date: 20-May-2010 7:53 AM CT Team met with John Snowden on site on Friday 5/21/10 to discuss what we should do south of Ponte. Mr. Snowden is an expert in grasses. In this meeting we discussed - anchoring the shoreline with sedges and rushes - mowing down the existing vegetation and hand raking the soil and spraying Inland Sea Oats, Canadian/Virginia Wild Rye and wheats/cerial rye. This work should not be done until September/October. - removing invasive species such as japanese honeysuckle, china berry, ect... Status: In Progress Assigned To: Eric Little Due Date: - TBA - NEW! Meeting Date: 15-Jul-2010 9:00 AM CT Discussed the following items that need to go back in front of CoE for possible changes: 1. Channel bottom - currently the mit plan states that the channel bottom must stay in place until the new creek walls are installed. The issue is the new walls are at a lower elevation than the existing channel bottom. 2. ABR is requesting to be able to add 3 low water crossings. 3. Creek bottom excavation at existing weir - vac vs excavation. Discussed NTC's pending dewater plan - need formal submittal. Status: In Progress Assigned To: Bruce Dunne Jennifer Haynes Brian LaFoy Due Date: - TBA - Topic 1.2 Construction Schedule In Progress -- Due Now Meeting Date: 17-Jun-2010 1:30 PM CT Median irrigation and landscaping is scheduled to start Monday, June 21st. NTC working on creek de-watering plan. This submittal is needs ASAP. Total of 23 piers have been drilled at Wildlife Observation Deck. Meeting scheduled with structural engineer scheduled for Friday, June 18th. Town still needs to tag the missing pond cypress, ash and crape myrtles. NTC to discuss with American. Status: In Progress Assigned To: Jennifer Haynes Due Date: - TBA - Meeting Date: 24-Jun-2010 9:00 AM CT Creek wall cut-in, grotto piers and median irrigation are all scheduled to start Monday Underground electric conduit and recirc waterlines are ongoing. Wildlife Observation piers are almost complete. Status: In Progress Assigned To: Jennifer Haynes Due Date: - TBA - Meeting Date: 8-Jul-2010 9:00 AM CT Irrigation has begun in the medians. The recirculation piping and the electrical conduit is ongoing. 38 of 65 piers are drilled at Wildlife Observation Deck. 9 of 10 piers are drilled at the Tree Preservation Deck. Soil Nail walls have begun. Testing of nails to be performed Friday, July 2nd at 9:00 AM. Kleinfelder and NDM to observe. 8ea of the 18" piers have been drilled at the grotto. Grading and mass excavation are ongoing. Status: In Progress Assigned To: Jennifer Haynes Due Date: - TBA - Meeting Date: 8-Jul-2010 9:00 AM CT Olden to finish upper lake walls this week and move to the west of the creek next week. Lower Sanitary Sewer manhole 7/8/2010 depending on weather Median irrigation ongoing Piers 11 & 12 at wildlife observation deck 3610psi for 28 day breaks Soil nail wall re-test Monday 7/12/2010 -- grout breaking over 5000 psi @ 7 days Status: In Progress Assigned To: Jennifer Haynes Due Date: - TBA - NEW! Meeting Date: 15-Jul-2010 9:00 AM CT Sanitary Sewer manhole lowered and backfilled. Upper lake walls complete. NTC is to submit a master schedule update at the next meeting. Status: In Progress Assigned To: Jennifer Haynes Due Date: - TBA - Topic 1.3 Phase IC - Change Order 2 In Progress -- Due Now Meeting Date: 6-May-2010 9:00 AM CT Review CO prepared by Bruce Dunn and advise of status of associated Change Order #6 for Phase IB. Status: In Progress Assigned To: Clay Barnett Bruce Dunne Eric Little Due Date: 7-May-2010 5:00 PM CT Meeting Date: 13-May-2010 9:00 AM CT Have received both CO #6 for Phase IB and CO #2 for 1C. Reviewing for approval. Status: In Progress Assigned To: Clay Barnett Eric Little Due Date: - TBA - Meeting Date: 17-Jun-2010 1:16 PM CT CO 6 and 2 are complete. CO 7 and 3 are pending Status: In Progress Assigned To: (none) Due Date: - TBA - Meeting Date: 24-Jun-2010 9:00 AM CT UDR to complete review of IB pay app, 1B CO #7 and 1C CO #3 today and forward comments to Town for review and approval. Once this is completed Town will present COs 2 and 3 to council for approval. (August) Status: In Progress Assigned To: Clay Barnett Due Date: - TBA - Meeting Date: 8-Jul-2010 9:00 AM CT COs #7, 2 and 3 are complete and pending approval by the Town. Status: In Progress Assigned To: Clay Barnett Due Date: - TBA - Topic 2.3 SWPPP Plan In Progress -- Due Now Meeting Date: 8-Jul-2010 9:00 AM CT Per Icon the Town can continue to use their existing NOI from 1B for the park. No new permit or filing is necessary. Status: In Progress Assigned To: (none) Due Date: - TBA - NEW! Meeting Date: 15-Jul-2010 9:00 AM CT Discussed revised design on rock check dam at existing weir. Status: In Progress Assigned To: Bruce Dunne Jennifer Haynes Brian LaFoy Due Date: - TBA - Topic 4.2 Submittals In Progress -- Due Now Meeting Date: 24-Jun-2010 9:00 AM CT Discussed the following submittals: 1. Dakota Granite (#2 - NTC) - Revise and Resubmit Pending NTC 2. Soil Nail Walls (#8 - NTC) - UDR forwarded to Kleinfelder and NDM for review - those comments are back - ball is in NTC's court. 3. Embeds at Wildlife Ob Deck (#9 - NTC) - Close this submittal. 4. Rebar Shops (#11 - NTC) - Pending Rebcon reply 5. False Weir (#12 - ICON) - Joel to review and comment 6. Signage (#13 - UDR) - UDR to review and comment 7. Screen Wall (#14 - Clay) - Town to review and approve color today 8. Electrical Submittal - UDR to re-open and edit with ICON comments 9. NTC to submit concrete pole colors for approval 10. NTC to submit creek dewater plan for comment and approval. Status: In Progress Assigned To: Clay Barnett Jennifer Haynes Eric Little Due Date: - TBA - Meeting Date: 8-Jul-2010 9:00 AM CT 1. Dakota Granite (#2 - NTC) - Revise and Resubmit Pending NTC 2. Soil Nail Walls (#8 - NTC) - Resubmit is complete. Will leave open until test reports are published. 3. Rebar Shops (#11 - NTC) - Rebcon has replied - pending Viewtech 4. False Weir (#12 - ICON) - Joel has reviewed - pending Viewtech 5. Signage (#13 - UDR) - Complete 6. Screen Wall (#14 - Clay) - Complete 7. Electrical Submittal - Resubmitted by NTC as Submittal #15 8. NTC to submit concrete pole colors for approval - Town approved #113 natural Gray Flat Sealer 9. NTC to submit creek dewater plan for comment and approval. Status: In Progress Assigned To: Jennifer Haynes Victor Lissiak III Joel Massey Due Date: - TBA - NEW! Meeting Date: 15-Jul-2010 9:00 AM CT 1. Dakota Granite (#2 - NTC) - Revise and Resubmit Pending NTC 2. Soil Nail Walls (#8 - NTC) - Resubmit is complete. Pending discussions with Kleinfelder and Olden. 3. Rebar Shops (#11 - NTC) - Viewtech replied. Pending NTC. 4. False Weir (#12 - ICON) - Joel has reviewed - pending Viewtech 5. Electrical Submittal - Resubmitted by NTC as Submittal #15 6. NTC to submit concrete pole colors for approval - Town approved #113 natural Gray Flat Sealer 7. NTC to submit creek dewater plan for comment and approval. 8. Screen Wall (#16) - pending discussion of who reviews (ToA requested NDM review). 9. Limstone Cap (#17) - Mock up has been reviewed - discuss attachment detail Status: In Progress Assigned To: Wade Geistweidt Jennifer Haynes Brian LaFoy Eric Little Joel Massey Due Date: - TBA - Topic 5.1 RFI Log In Progress -- Due Now Meeting Date: 8-Jul-2010 9:00 AM CT #10 - Interior (Belled) Piers at Wildlife Observation Deck - Open in Rebcon's court #11 - Storm Junction Box Cover - (ICON) - COMPLETE #13 - False Weir - (Greenscapes) - Pending Viewtech comments #14 - False Weir fill valve - (Greenscapes) - Pending ICON and Greenscape's comments #16 - Exposed Conduits at Grotto - (Kevin Slone) - ICON and KSS have replied, pending Viewtech comments. Status: In Progress Assigned To: Jennifer Haynes Victor Lissiak III Joel Massey Due Date: - TBA - NEW! Meeting Date: 15-Jul-2010 9:00 AM CT #10 - Interior (Belled) Piers at Wildlife Observation Deck - Open in Rebcon's court #13 - False Weir - (Greenscapes) - COMPLETE #14 - False Weir fill valve - (Greenscapes) - Pending ICON and Greenscape's comments #16 - Exposed Conduits at Grotto - (Kevin Slone) - ICON and KSS have replied, pending Viewtech comments. Discussed #22 - Expansion and Construction Joints being critical. NTC to write RFI concerning low breaks on piers. Status: In Progress Assigned To: Jennifer Haynes Joel Massey Due Date: - TBA - Topic 5.3 Corridination Between Bridge Package and Park Package In Progress -- Due Now Meeting Date: 8-Jul-2010 9:00 AM CT ICON has received CAD drawings. Indicates that their are some more design issues that need to be solved. Will send over list in writing prior to meeting next Thursday. Status: In Progress Assigned To: Eric Christiansen Joel Massey Due Date: - TBA - NEW! Meeting Date: 15-Jul-2010 9:00 AM CT Need to discuss results of design coordination meeting. Status: In Progress Assigned To: Eric Christiansen Bruce Dunne Joel Massey Due Date: - TBA - Topic 5.4 Limestone Caps at Creek Walls In Progress -- Due Now Meeting Date: 17-Jun-2010 1:30 PM CT NTC stated that they can provide limestone caps at no additional cost on the creek walls. This option was on the table originally, but cost and durablity issues shelved it. Need final detirmination on this ASAP. Status: In Progress Assigned To: Clay Barnett Eric Little Due Date: - TBA - Meeting Date: 8-Jul-2010 9:00 AM CT Connection detail needed for limestone caps. Status: In Progress Assigned To: (none) Due Date: - TBA - NEW! Meeting Date: 15-Jul-2010 9:00 AM CT NTC drilled through the tops of the caps and anchored with grout. ToA and UDR do not like. Discuss alternate attachment detail. Status: In Progress Assigned To: Jennifer Haynes Eric Little Due Date: - TBA - Topic 6.1 Fire Hydrant Usage In Progress -- Due Now Meeting Date: 24-Jun-2010 9:00 AM CT When using hydrants for water, please make sure the valve is opened all the way. Status: In Progress Assigned To: Jennifer Haynes Due Date: - TBA - NEW! Meeting Date: 15-Jul-2010 9:00 AM CT Closed. Status: Complete Assigned To: (none) Due Date: - TBA - Topic 6.2 Water Well In Progress -- Due Now Meeting Date: 24-Jun-2010 9:00 AM CT ICON still attempting to get pricing from local drillers to do this. So far no response. Status: In Progress Assigned To: Bruce Dunne Due Date: - TBA - Topic 6.3 Bridge Ped Rail Usage in Park In Progress -- Due Now Meeting Date: 24-Jun-2010 9:00 AM CT Town would like to look at using the vertical cable rail currently designed on the bridge through-out the park. UDR to send NTC detail for pricing. Status: In Progress Assigned To: Jennifer Haynes Eric Little Due Date: - TBA - Meeting Date: 8-Jul-2010 9:00 AM CT UDR has send detail. Pending NTC pricing. Status: In Progress Assigned To: Jennifer Haynes Due Date: - TBA - Topic 6.4 Street Fountain Installation In Progress -- Due Now Meeting Date: 24-Jun-2010 9:00 AM CT The following items were discussed on the fountain: 1. Who is removing the pavers currently installed where the fountain is to be installed? 2. RPZ is still an issue. Need to work out location and design of hot box. 3. ICON needs cutsheets for vault 4. ICON to set up a meeting with ToA to discuss RPZ Status: In Progress Assigned To: Jennifer Haynes Joel Massey Due Date: 30-Jun-2010 5:00 PM CT Meeting Date: 8-Jul-2010 9:00 AM CT ICON submitted drawings for discussion. UDR to review and approve. Attachment: Vitruvian Park Street Fountain Equipment Exhibits.msg Status: In Progress Assigned To: Eric Little Due Date: - TBA - NEW! Meeting Date: 15-Jul-2010 9:00 AM CT Closed. Design issues approved by UDR and ToA. Status: Complete Assigned To: (none) Due Date: - TBA - Topic 6.5 Recirculation System Routing In Progress -- Due Now Meeting Date: 24-Jun-2010 9:00 AM CT NTC requests that ICON review the routing of this piping at the existing TxDOT bridge. They would like to move the open cut crossing so that they can complete the loop. ICON to review and advise. Status: In Progress Assigned To: Bruce Dunne Joel Massey Due Date: - TBA - NEW! Meeting Date: 15-Jul-2010 9:00 AM CT ICON advised that piping is to be installed per the current design. Status: Complete Assigned To: (none) Due Date: - TBA - Topic 6.6 Epoxy Coated Rebar In Progress -- Due Now Meeting Date: 24-Jun-2010 9:00 AM CT NTC requested review of direction from ICON that epoxy coated rebar was not required at the areas exposed to water. ICON to discuss with Viewtech and reply back. Status: In Progress Assigned To: Bruce Dunne Due Date: - TBA - NEW! Meeting Date: 15-Jul-2010 9:00 AM CT Closed. Status: Complete Assigned To: (none) Due Date: - TBA - Topic 8.1 construction entrance In Progress -- Due Now Meeting Date: 8-Jul-2010 9:00 AM CT NTC to install a construction entrance -- discuss with UDR regarding size and coordination for install. Status: In Progress Assigned To: Jennifer Haynes Due Date: - TBA - NEW! Meeting Date: 15-Jul-2010 9:00 AM CT NTC to meet with Andres next week. Status: In Progress Assigned To: Jennifer Haynes Due Date: - TBA - Topic 8.2 COE In Progress -- Due Now Meeting Date: 8-Jul-2010 9:00 AM CT Icon to discuss with KBA regarding re-visiting with the COE regarding the concrete liner and silt removal at teh weir. De-water plan is critical for this meeting. Status: In Progress Assigned To: Bruce Dunne Jennifer Haynes Due Date: - TBA - New Business No new items to display. Addendum N/A .................................................................................. Copyright (c) 1999-2010, Systemates, Inc. View the User Agreement for legal restrictions and terms of use applicable to this site. Use of this site signifies your agreement to the terms of use specified in the User Agreement. Projectmates - The Capital Project Management Software ꡯᴡ�欠䃲掰〙뇰ゞႫ滞煁僢催hᶰ﵁瓿옮묟홿힟マ쿧�↑3࿭￘翃᣿᤿읏ᬟ둯ᴏẏᾟᆵ뼠뾸㿸D�﷿️?Я�ቯ፟ッ輚輕鼖U浃輤釯♊饿髟㧬ᇝ탢旐냮†摤熬냢꣯⬁걒ⰵ戃耊샵鄊꡿꜁੶ⶐ᥉₋搡₿Ựᨰダ珰炞᫿齯ǖㆿꛏ꟟䖟픴満晩Ⴋ렠慈ṹـᄬ慄󿳟㗯㙏㝟㵯䗁郮揨䰠㧐㪟뾯뼻켼伨弩羛夜ᤰa聄ȫ漤꼽涞䬲ཀ釟䬽ᢟ᧯엿疰싅⍗␿╏ⵗ#ⶀ凿劯莿퍟풿减孟屿マ齝꽞뽟콠�」ཥ替期栯椿橏歟 汯浿マ齮꽯뽰콱�エྲྀ矿砟礯稿筏籟絯繿マ齿꾀뾁쾂�ナ྇裿褟訯謿豏赟蹯轿マ龐꾑뾒㽚뼟켠뼗輜᷿鎟鞿颿髏嘕먯?鼧罙弐썈ꅄ辝龞䮙ꏿꕟ䣒鬋䛗䟯䧿倏a辨㽉佊ᾡ쾯�⫳⟳ⴧⷿⲆ⭞}缯輰쾴�нퟂ屃㋷鱷玀෣_῀�꠿ꥏ롟쌁㹯睐イ郰㞺뀿濢꿆뿇㽘ꐗ튿⌣瀐煁⸶Q࿒㧊뾿俋ᄋ䓿䔯㴿㻟콲큿駖倭摬࿑㓟楆怍㦝礠胮₣《獕゛䇿���㺏췺쿐ミ僯⧐倫 老バ哎࿤िયி೏埛坰咀﹒칎ຏힿ�꨿￟￧࿺鿍ꃎ鿫运忮� 쩿闟錿슺留؟?㿻俼ἂ⼃義꾬뾭쾮샿뚿�댟쀿ጿᒟ徸̫⃆⯰Ӏ秀삹㩹