New RFI No. 23 As of 15-Jul-2010 11:19 AM CT Vitruvian Infrastructure Phase 1C Park 4010 Marsh Lane Addison, Texas 75001 Project Number: 1308C Status: Outstanding Subject Low Breaks on Piers Reason Code None Question Piers 11 and 12 broke at an average of 3610 psi with a requirement of 4000 psi. Kleinfelder sent me breaks for 3 days prior and 3 days after and they average 4964 psi. Please advise. Proposed Solution Attached Files (none) Section: 3 - Concrete Int. Tracking #: Days Elapsed: 0 From: Jennifer Haynes Originated: 15-Jul-2010 11:19 AM CT To: Nick Jacob (First Recipient) Requested By: 18-Jul-2010 11:12 AM CT Copy to: Joel Massey Eric Little Victor Lissiak III Mark Gaines Deiadra Burns Clay Barnett Additional Info Proposed Solution Impact Critical Path? No Cost Change: None Time Change: None Discipline Code: Structural Drawing Numbers: Needs Drawing Change? N/A History (Chronological Order) No history to display. Final Response (Closing) This item is still open. No final response to display. .................................................................................. Copyright (c) 1999-2010, Systemates, Inc. View the User Agreement for legal restrictions and terms of use applicable to this site. Use of this site signifies your agreement to the terms of use specified in the User Agreement. Projectmates - The Capital Project Management Software