Response to RFI No. 22 As of 13-Jul-2010 3:53 PM CT Vitruvian Infrastructure Phase 1C Park 4010 Marsh Lane Addison, Texas 75001 Project Number: 1308C Status: Outstanding Overdue Subject Expansion and Construction Joints Reason Code None Question SP311 doesn't show any construction or expansion Joints. What is the minimum spacing for these? Also there are construction joints show on the Wildlife and Belvedere walls but no detail on them. There is a detail on Sheet SP300 that appears to be for the sidewalk walls but the keyway might look bad coming to the top of the wall and stopping the forms every 8 ft or so will make it diffucult to hold a smooth radius. There was a detail on SP300 for crack control joints that was removed, can that be used at the construction joint locations? Also the Belvedere walls sheet L7-02 show a tooled joint in between the construction joint. Is this just on the top or was that meant to be a reveal that goes vertically in the wall and on top, again the crack control detail that was deleted from sheet SP300 would seem appropriate for this scenario. The Grotto walls, Stairs, Ramps, Walls around the Fords all need this clarified also. Proposed Solution Attached Files (none) Section: 3 - Concrete Int. Tracking #: Days Elapsed: 4 From: Jennifer Haynes Originated: 9-Jul-2010 1:12 PM CT To: Nick Jacob (First Recipient) Requested By: 12-Jul-2010 12:00 AM CT (Original 12-Jul-2010 1:09 PM CT) Copy to: Joel Massey Eric Little Victor Lissiak III Wade Geistweidt Mark Gaines Clay Barnett Additional Info Proposed Solution Impact Critical Path? Yes Cost Change: None Time Change: None Discipline Code: Structural Drawing Numbers: Needs Drawing Change? Yes History (Chronological Order) Type Routed Billable n/a Memo please advise Attached Files (none) From: Nick Jacob Sent: 9-Jul-2010 1:16 PM CT To: Victor Lissiak III Requested By: 12-Jul-2010 1:09 PM CT Copy to: (none) Type Routed Billable n/a Memo This item is currently overdue and per NTC they need a response today. Please address this item ASAP. Attached Files (none) From: Nick Jacob Sent: 13-Jul-2010 3:27 PM CT To: Victor Lissiak III Requested By: 12-Jul-2010 1:09 PM CT Copy to: Eric Little Jennifer Haynes Type Response Billable n/a Memo Details 10 and 11 were inadvertantly removed from SP300. Those details are typical crack control joint details and have been restored in the attached revised detail sheet. Details 10 and 11 are for crack mitigation, not construction joints. Detail 9 is the detail for construction joints. Attached Files SP300-REV 7-13-10.pdf From: Victor Lissiak III Sent: 13-Jul-2010 3:53 PM CT To: Nick Jacob Requested By: 12-Jul-2010 12:00 AM CT Copy to: Joel Massey Eric Little Wade Geistweidt Mark Gaines Clay Barnett Final Response (Closing) This item is still open. No final response to display. .................................................................................. Copyright (c) 1999-2010, Systemates, Inc. View the User Agreement for legal restrictions and terms of use applicable to this site. Use of this site signifies your agreement to the terms of use specified in the User Agreement. Projectmates - The Capital Project Management Software