>> Leave comment << Response to RFI No. 52 As of 25-Jan-2011 1:42 PM CT Vitruvian Infrastructure Phase 1C Park 4010 Marsh Lane Addison, Texas 75001 Project Number: 1308C Status: Outstanding Overdue Subject Grotto Waterfall Pool Reason Code None Question The topping slab on the grotto waterfall pool does not show any reinforcement. We are concerned that this being a cold joint, it could eventually sluff off. Please provide direction. Proposed Solution Attached Files (none) Section: 2 - Sitework Int. Tracking #: Days Elapsed: 49 From: Jennifer Haynes Originated: 7-Dec-2010 2:57 PM CT To: Nick Jacob (First Recipient) Requested By: 10-Dec-2010 12:00 AM CT (Original 10-Dec-2010 2:51 PM CT) Copy to: Jerry West Eric Little Robyn Jacobson Wade Geistweidt Clay Barnett Additional Info Proposed Solution Impact Critical Path? Yes Cost Change: Yes, may be Time Change: None Discipline Code: N/A Drawing Numbers: Needs Drawing Change? Yes History (Chronological Order) Type Routed Billable n/a Memo The topping slab on the grotto waterfall pool does not show any reinforcement. We are concerned that this being a cold joint, it could eventually sluff off. Please provide direction. Attached Files (none) From: Nick Jacob Sent: 8-Dec-2010 9:54 AM CT To: Victor Lissiak III Requested By: 10-Dec-2010 2:51 PM CT Copy to: Robyn Jacobson Type Response Billable n/a Memo Please reference a particular plan or section. Thank you. Attached Files (none) From: Victor Lissiak III Sent: 14-Dec-2010 9:03 AM CT To: Nick Jacob Requested By: 10-Dec-2010 12:00 AM CT Copy to: Eric Little Jennifer Haynes Type Routed Billable n/a Memo Please reference a particular plan or section Attached Files (none) From: Nick Jacob Sent: 20-Dec-2010 11:40 AM CT To: Jennifer Haynes Requested By: 10-Dec-2010 12:00 AM CT Copy to: Eric Little Victor Lissiak III Type Routed Billable n/a Memo Joel, This is the RFI discussed in last Tuesday's meeting. I spoke with Greenscapes and they wish to just delete this topping slab all together. Attached Files (none) From: Eric Little Sent: 27-Dec-2010 8:39 AM CT To: Joel Massey Requested By: 10-Dec-2010 12:00 AM CT Copy to: Nick Jacob Jennifer Haynes Clay Barnett Type Routed Billable n/a Memo Please see attached detail sheet showing the reinforcement for the topping slab. Attached Files 6475 Sidewalk_I101-M101-M104-D101-D104_042610 D102 01-13-11.pdf From: Jennifer Haynes Sent: 25-Jan-2011 1:42 PM CT To: Eric Little Requested By: 10-Dec-2010 12:00 AM CT Copy to: Joel Massey Robyn Jacobson Clay Barnett Final Response (Closing) This item is still open. No final response to display. .................................................................................. Copyright (c) 1999-2011, Systemates, Inc. View the User Agreement for legal restrictions and terms of use applicable to this site. Use of this site signifies your agreement to the terms of use specified in the User Agreement. Projectmates - The Capital Project Management Software