>> Leave comment << Response to RFI No. 69 As of 25-May-2011 10:11 AM CT Vitruvian Infrastructure Phase 1C Park 4010 Marsh Lane Addison, Texas 75001 Project Number: 1308C Status: Complete Subject Pergola Reason Code None Question On Sheet L9-12, Detail 4, it indicates that the 3"x1-1/2" steel on top of the pergola be oriented such that the 3" dimension is vertical. Sheet SP308 contradicts that detail. Please advise which way the steel is to be mounted? Proposed Solution Attached Files (none) Section: 5 - Metals Int. Tracking #: Days Elapsed: 0 From: Jennifer Haynes Originated: 12-May-2011 3:12 PM CT To: Nick Jacob (First Recipient) Requested By: 15-May-2011 12:00 AM CT (Original 15-May-2011 3:09 PM CT) Copy to: Joel Massey Eric Little Victor Lissiak III Robyn Jacobson Wade Geistweidt Clay Barnett Additional Info Proposed Solution Impact Critical Path? Yes Cost Change: None Time Change: None Discipline Code: N/A Drawing Numbers: Needs Drawing Change? Yes History (Chronological Order) Type Routed Billable n/a Memo please advise Attached Files (none) From: Nick Jacob Sent: 18-May-2011 9:01 AM CT To: Robyn Jacobson Requested By: 15-May-2011 3:09 PM CT Copy to: Eric Little Victor Lissiak III Final Response (Closing) Response We have not gotten a response from any of the design consultants, so I'll make an executive decision and direct you to follow the design intent shown on L9-12, Detail 4. Thanks, Eric Billable n/a Attached Files (none) From: Eric Little Sent: 25-May-2011 10:11 AM CT To: Jennifer Haynes Copy to: Joel Massey Victor Lissiak III Robyn Jacobson Wade Geistweidt Clay Barnett .................................................................................. Copyright (c) 1999-2011, Systemates, Inc. View the User Agreement for legal restrictions and terms of use applicable to this site. Use of this site signifies your agreement to the terms of use specified in the User Agreement. Projectmates - The Capital Project Management Software