Clay, The 1D Pay App appears to be good to go now. Thanks, Eric -----Original Message----- From: Andrew Harper [mailto:AHarper@Austin-Ind.com] Sent: Tuesday, May 03, 2011 8:22 AM To: Eric T. Little Subject: Re: April 2011 Pay App The LED light strips are finished, except for actually connecting them. They're waiting on the stone. He said it wouldn't take but half a day to complete them. You want me to change it to 90%? The Type F fixtures are installed. They're covered in plastic and cardboard for protection until the sandblasting is done. On May 3, 2011, at 8:09 AM, "Eric T. Little" wrote: > Andrew, > > The only issues I have with this are items 28 and 29. You are billing 100%, but I don’t believe they are installed yet. > > Take a look at get back to me. > > Thanks, > > Eric > > From: Andrew Harper [mailto:AHarper@Austin-Ind.com] > Sent: Monday, May 02, 2011 11:21 AM > To: Eric T. Little; Nick Jacob > Cc: Todd Henson > Subject: April 2011 Pay App > > > > Andrew Harper | Project Coordinator > > AUSTIN BRIDGE & ROAD > IH30/PGBT Interchange Lake Ray Hubbard – 608006 > Addison Vitruvian Park Bridges - 610007 > > 1013 I-30 East > Garland, TX 75043 > 214.886.6666 (M) > 972.240.6200 (O) > 972.240.6204 (F) > >