FYI – looks like we are in the clear with Austin. Thanks, Eric Little Project Manager, UDR 5430 LBJ Freeway, Suite 1250 Dallas, TX 75240 Ph: 972.774.0552 Fx: 972.991.4113 Cell: 214.641.5761 www.UDR.com From: Todd Henson [mailto:THenson@Austin-Ind.com] Sent: Tuesday, August 03, 2010 9:30 AM To: Eric T. Little Cc: Nick Jacob; Andrew Harper; ABR610007 Subject: Schedule Revision Eric, By adjusting the schedule as discussed with North Texas and Rebcon, we were able to shorten the overall duration from 295 days to under the allowed 240 days. We will submit the revised schedule to you at our Thursday meeting. Todd Henson Sr. Project Manager Austin Bridge & Road 214-681-2128