Todd, Please execute this and email back. Thanks, From: Clay Barnett [mailto:cbarnett@addisontx.gov] Sent: Friday, November 12, 2010 10:46 AM To: Eric T. Little Cc: Tom Frazier; Nick Jacob; Wade Geistweidt (wgeistweidt@kleinfelder.com) (wgeistweidt@kleinfelder.com) ; Tom Forrest Subject: RE: Pay Apps Phases 1C and 1D Eric, Attached is the pay application for the bridges. Please have it executed by the contractor and returned for payment. Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857 From: Eric T. Little [mailto:ELittle@udr.com] Sent: Monday, November 08, 2010 11:24 AM To: Clay Barnett Cc: Tom Frazier; Nick Jacob; Wade Geistweidt (wgeistweidt@kleinfelder.com) (wgeistweidt@kleinfelder.com); Tom Forrest Subject: Pay Apps Phases 1C and 1D Clay, Here are the final pay apps for October – both with contractor corrections received on Friday of last week. Please let us know if you have any questions or concerns. Thanks, Eric