Eric,
I am working on the pay application and noticed on Item 87 that we exceeded the amount in the contract. Is this correct? If so I will go ahead and overrun the quantity and we can add
it to the change order when available.
Thanks,
Clay Barnett, P.E.
Town Engineer
Town of Addison
16801 Westgrove Drive
Addison, TX 75001-2818
Office: (972) 450-2857
From: Eric T. Little [mailto:ELittle@udr.com]
Sent: Wednesday, June 01, 2011 2:54 PM
To: Clay Barnett
Cc: Robert Farrow; Nick Jacob; 'wgeistweidt@kleinfelder.com'
Subject: FW: 2A Bella - May Pay App
Clay,
Here is the final version of the 2A pay app for May. Let me know if you have any questions.
Thanks,
Eric
From: Eric T. Little
Sent: Wednesday, June 01, 2011 11:50 AM
To: 'Robert Farrow'
Subject: RE: 2A Bella - May Pay App
Here is the corrected version.
Thanks,
Eric
From: Robert Farrow [mailto:rfarrow@concretepaversystems.com]
Sent: Wednesday, June 01, 2011 11:41 AM
To: Eric T. Little
Subject: Re: 2A Bella - May Pay App
Let me know I know we called the core driller yesterday
Sent from my iPhone
On Jun 1, 2011, at 11:40 AM, "Eric T. Little" wrote:
Well, the guy responsible for inspecting them says they aint. Let me get with Wade and get back to you.
From: Robert Farrow [mailto:rfarrow@concretepaversystems.com]
Sent: Wednesday, June 01, 2011 11:40 AM
To: Eric T. Little
Subject: Re: 2A Bella - May Pay App
I just spoke to Scott. He says all three manholes are in and were yesterday ? Please confirm
Sent from my iPhone
On Jun 1, 2011, at 11:30 AM, "Eric T. Little" wrote:
Robert,
Here are my mark-ups to your pay app.
#6 – reduced to $0 this period as no work has been done to date on the new construction entrance.
#64 – reduced to 1ea manhole.
Please review and let me know if you have any issues with this. If not, I’ll forward on to the Town to process.
Thanks,
Eric