Clay, Just realized we still had $11K still in MOH. Here it is with the MOH zeroed out since CO #3 will be paid this month. Thanks, Andrew Harper Cell (214) 886-6666 From: Eric T. Little [mailto:ELittle@udr.com] Sent: Thursday, July 07, 2011 9:02 AM To: 'Clay Barnett' Cc: Nick Jacob; 'Wade Geistweidt'; Andrew Harper Subject: FW: Phase 1D - Bridges - Jun Pay App Clay, Here is the June pay app for Phase 1D. We have reviewed it and did not see any needed corrections. Please let me know if you have any questions or comments. Thanks, Eric From: Andrew Harper [mailto:AHarper@Austin-Ind.com] Sent: Thursday, June 30, 2011 5:23 PM To: Eric T. Little; Nick Jacob Cc: Todd Henson Subject: Jun Pay App I’ve included CO #3 in this month’s pay app. Let me know if I need to change anything. Also, we are still waiting on the fugitive dye to come in from Quality Paint Products in Minnesota. Scott Derr has bugged them for the past 2 weeks trying to get it from them. Hopefully we’ll see it tomorrow or first of next week. Thanks, Andrew Harper | Project Coordinator AUSTIN BRIDGE & ROAD IH30/PGBT Interchange Lake Ray Hubbard – 608006 Addison Vitruvian Park Bridges - 610007 1013 I-30 East Garland, TX 75043 214.886.6666 (M) 972.240.6200 (O) 972.240.6204 (F)