Eric, The revised pay application is attached. Please have it executed and returned for payment. Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857 From: Eric T. Little [mailto:ELittle@udr.com] Sent: Friday, July 15, 2011 7:54 AM To: Clay Barnett Cc: Nick Jacob; 'Wade Geistweidt'; 'Andrew Harper' Subject: RE: Phase 1D - Bridges - Jun Pay App Clay, Here is what Andrew and I talked about this morning: #1 – Mobilization – Take up to 100%. #3 – SWPPP Maintenance – Take up to 100%. #4 – Project Signs – I should have added this to CO3 – we only had them put up one sign. Need to create CO4 and add this to it. #16 – Pending re-set of the arch rods. CO3- 5 – Pending solution to microbubble issue. CO3-6 – This has been removed from their scope. Once Andrew gives be the breakdown on the material $, we can add the deleted labor to CO4. Thanks, Eric From: Clay Barnett [mailto:cbarnett@addisontx.gov] Sent: Wednesday, July 13, 2011 3:37 PM To: Eric T. Little Cc: Nick Jacob; 'Wade Geistweidt'; 'Andrew Harper' Subject: RE: Phase 1D - Bridges - Jun Pay App Eric, Before it is executed, could we check and zero out all of the items that they have completed (i.e. Mobilization and SWPPP Maintenance)? Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857 From: Clay Barnett Sent: Wednesday, July 13, 2011 2:32 PM To: Eric T. Little Cc: Nick Jacob; 'Wade Geistweidt'; 'Andrew Harper' Subject: RE: Phase 1D - Bridges - Jun Pay App Eric, Attached is Pay Application 11. Please have it executed and returned for payment. Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857 From: Andrew Harper [mailto:AHarper@Austin-Ind.com] Sent: Thursday, July 07, 2011 9:20 AM To: Eric T. Little; Clay Barnett Cc: Nick Jacob; 'Wade Geistweidt' Subject: RE: Phase 1D - Bridges - Jun Pay App Clay, Just realized we still had $11K still in MOH. Here it is with the MOH zeroed out since CO #3 will be paid this month. Thanks, Andrew Harper Cell (214) 886-6666 From: Eric T. Little [mailto:ELittle@udr.com] Sent: Thursday, July 07, 2011 9:02 AM To: 'Clay Barnett' Cc: Nick Jacob; 'Wade Geistweidt'; Andrew Harper Subject: FW: Phase 1D - Bridges - Jun Pay App Clay, Here is the June pay app for Phase 1D. We have reviewed it and did not see any needed corrections. Please let me know if you have any questions or comments. Thanks, Eric From: Andrew Harper [mailto:AHarper@Austin-Ind.com] Sent: Thursday, June 30, 2011 5:23 PM To: Eric T. Little; Nick Jacob Cc: Todd Henson Subject: Jun Pay App I’ve included CO #3 in this month’s pay app. Let me know if I need to change anything. Also, we are still waiting on the fugitive dye to come in from Quality Paint Products in Minnesota. Scott Derr has bugged them for the past 2 weeks trying to get it from them. Hopefully we’ll see it tomorrow or first of next week. Thanks, Andrew Harper | Project Coordinator AUSTIN BRIDGE & ROAD IH30/PGBT Interchange Lake Ray Hubbard – 608006 Addison Vitruvian Park Bridges - 610007 1013 I-30 East Garland, TX 75043 214.886.6666 (M) 972.240.6200 (O) 972.240.6204 (F) ************************************************************ This e-mail and any files or attachments transmitted with it contain Information that is confidential and privileged. This document may contain Protected Health Information (PHI) or other information that is intended only for the use of the individual(s) and entity(ies) to whom it is addressed. If you are the intended recipient, further disclosures are prohibited without proper authorization. If you are not the intended recipient, any disclosure, copying, printing, or use of this information is strictly prohibited and possibly a violation of federal or state law and regulations. If you have received this information in error, please delete it and notify Hamid Khaleghipour at 972-450-2868 immediately. Thank you. ************************************************************