The price for the railing and stone veneer is locked in on the contract. Same with the handrail. Neither party can change it unless it increases or decreases by 25%. I just did not know if the quantities were correct. We could leave it off, but that would not look very good, so I think we just include it at the unit price in the contract. Sounds like the only issue may be the cost of the retaining wall. Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857 From: Christiansen, Eric [mailto:echristiansen@halff.com] Sent: Thursday, September 09, 2010 6:28 PM To: Clay Barnett Subject: RE: Vit Park - Phase ID - Austin Change Order #01 Pricing Clay, I've been considering the wall unit price and I am concerned. The price is more than double what I would expect to pay ($50/SF) for a large wall. While I understand that average prices need to be increased for small projects, Austin's rate ($112/SF) seems a bit excessive. I've left Eric Little a message to call me so we can put our heads together Friday morning; I'll contact you after he and I have had a chance to talk. I can answer your question about stone veneer. The intent of our design was to add the veneer to the wall since it is immediately adjacent to the veneered abutment of Bella Lane. It makes sense, but the $26,560 price sours the deal. It sounds like you would agree? I'll be in touch sometime Friday morning. Eric Eric S. Christiansen, P.E., SECB, LEED AP Senior Structural Engineer HALFF ASSOCIATES, INC. 1201 North Bowser Road Richardson, Texas 75081 Phone 214-346-6284 Fax 214-739-0095 Cell 972-955-2996 www.halff.com From: Clay Barnett [mailto:cbarnett@addisontx.gov] Sent: Thursday, September 09, 2010 3:15 PM To: Christiansen, Eric Cc: Nick Jacob; Tom Lamberth; 'Eric T. Little' Subject: RE: Vit Park - Phase ID - Austin Change Order #01 Pricing Eric, Could you double check the wall prices and make sure they make sense? I can understand the additional handrail, but the additional stone veneer? Where is it going? Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857 From: Eric T. Little [mailto:ELittle@udr.com] Sent: Thursday, September 09, 2010 2:57 PM To: Christiansen, Eric; Clay Barnett Cc: Nick Jacob; Tom Lamberth Subject: Vit Park - Phase ID - Austin Change Order #01 Pricing Eric/Clay: Here is the pricing for the electrical changes and the new retaining walls at Bella. Please review and comment. Thanks, Eric Little Project Manager, UDR 5430 LBJ Freeway, Suite 1250 Dallas, TX 75240 Ph: 972.774.0552 Fx: 972.991.4113 Cell: 214.641.5761 www.UDR.com ****************************************************************************************************************** This e-mail and any files or attachments transmitted with it contains Information that is confidential and privileged. This document may contain Protected Health Information (PHI) or other information that is intended only for the use of the individual(s) and entity(ies) to whom it is addressed. If you are the intended recipient, further disclosures are prohibited without proper authorization. If you are not the intended recipient, any disclosure, copying, printing, or use of this information is strictly prohibited and possibly a violation of federal or state law and regulations. If you have received this information in error, please delete it and notify Hamid Khaleghipour at 972-450-2868 immediately. Thank you. *******************************************************************************************************************