Yes sir –
5 days for the rebar is legit.
2 days for the grounding seems fair.
16 days for COE is what we agreed to.
Thanks,
Eric
From: Clay Barnett [mailto:cbarnett@addisontx.gov]
Sent: Wednesday, November 17, 2010 8:34 AM
To: Eric T. Little
Cc: Tom Forrest; Tom Lamberth; Nick Jacob
Subject: RE: Vitruvian - Change Order #1 Mods
What about the total number of days given?
Clay Barnett, P.E.
Town Engineer
Town of Addison
16801 Westgrove Drive
Addison, TX 75001-2818
Office: (972) 450-2857
From: Eric T. Little [mailto:ELittle@udr.com]
Sent: Wednesday, November 17, 2010 8:32 AM
To: Clay Barnett
Cc: Tom Forrest; Tom Lamberth; Nick Jacob
Subject: RE: Vitruvian - Change Order #1 Mods
Yes sir. Five days is reasonable for the amount of work and the delays associated with the rebar changes.
From: Clay Barnett [mailto:cbarnett@addisontx.gov]
Sent: Wednesday, November 17, 2010 8:30 AM
To: Eric T. Little
Cc: Tom Forrest; Tom Lamberth; Nick Jacob
Subject: RE: Vitruvian - Change Order #1 Mods
Eric,
Are you OK with the 3rd paragraph and the number of days requested? If so, I will get it to Eric C. and get started on CO #2.
Thanks,
Clay Barnett, P.E.
Town Engineer
Town of Addison
16801 Westgrove Drive
Addison, TX 75001-2818
Office: (972) 450-2857
From: Eric T. Little [mailto:ELittle@udr.com]
Sent: Wednesday, November 17, 2010 8:14 AM
To: Clay Barnett
Cc: Tom Forrest; Tom Lamberth; Nick Jacob
Subject: RE: Vitruvian - Change Order #1 Mods
Clay,
As far as I can tell, the pricing in this change order is legit. The subcontractor who is installing the grounding system is the same sub who installed the lightning protection system
on Savoye and from what I can gather the pricing for the system spec’ed on the bridges lines up with what people I know would expect.
Let me know if you have any questions or concerns.
Thanks,
From: Clay Barnett [mailto:cbarnett@addisontx.gov]
Sent: Friday, November 12, 2010 4:02 PM
To: Eric T. Little
Cc: Tom Forrest; 'Todd Henson'
Subject: RE: Vitruvian - Change Order #1 Mods
Eric,
As was discussed in the meeting yesterday, could we go ahead and execute CO 1 for the bridge and place the remaining items on a list for CO #2? If so, CO 1 is attached and ready to be
executed.
Thanks,
Clay Barnett, P.E.
Town Engineer
Town of Addison
16801 Westgrove Drive
Addison, TX 75001-2818
Office: (972) 450-2857
From: Christiansen, Eric [mailto:echristiansen@halff.com]
Sent: Wednesday, October 20, 2010 1:50 PM
To: Clay Barnett
Cc: Tom Forrest; 'Eric T. Little'; 'Todd Henson'
Subject: RE: Vitruvian - Change Order #1 Mods
Importance: High
Per Clay's request, Change Order #1 has been modified to reflect quantity adjustments in the field. You'll find these corrections on the attached document. Feel free to contact me with
further questions or clarifications.
Eric S. Christiansen, P.E., SECB, LEED AP
Senior Structural Engineer
HALFF ASSOCIATES, INC.
1201 North Bowser Road
Richardson, Texas 75081
Phone 214-346-6284
Fax 214-739-0095
Cell 972-955-2996
www.halff.com
From: Clay Barnett [mailto:cbarnett@addisontx.gov]
Sent: Tuesday, October 19, 2010 11:03 AM
To: Christiansen, Eric
Cc: Tom Forrest; 'Eric T. Little'; 'Todd Henson'
Subject: RE: Vitruvian - Quantity Mods
Eric,
Additionally on Change Order #1, please change Item 77 to CO1-1 and CO1-1 to CO1-2 since Item 77 was not in the original bid.
Thanks,
Clay Barnett, P.E.
Town Engineer
Town of Addison
16801 Westgrove Drive
Addison, TX 75001-2818
Office: (972) 450-2857
From: Clay Barnett
Sent: Tuesday, October 19, 2010 10:54 AM
To: 'Christiansen, Eric'
Cc: Tom Forrest; 'Eric T. Little'; 'Todd Henson'
Subject: RE: Vitruvian - Quantity Mods
Eric,
It appears that we over ran the quantity on pier depths. They are as follows:
Item Desc Unit Change
BID-7 Drilled Shafts (48 IN) 26
BID-8 Drilled Shafts (54 IN) 1.4
Could you add these two to the change order and send it back to Austin to execute?
Thanks,
Clay Barnett, P.E.
Town Engineer
Town of Addison
16801 Westgrove Drive
Addison, TX 75001-2818
Office: (972) 450-2857
******************************************************************************************************************
This e-mail and any files or attachments transmitted with it contains Information that is confidential and privileged. This document may contain Protected Health Information (PHI) or
other information that is intended only for the use of the individual(s) and entity(ies) to whom it is addressed. If you are the intended recipient, further disclosures are prohibited
without proper authorization. If you are not the intended recipient, any disclosure, copying, printing, or use of this information is strictly prohibited and possibly a violation of
federal or state law and regulations. If you have received this information in error, please delete it and notify Hamid Khaleghipour at 972-450-2868 immediately. Thank you.
*******************************************************************************************************************
******************************************************************************************************************
This e-mail and any files or attachments transmitted with it contains Information that is confidential and privileged. This document may contain Protected Health Information (PHI) or
other information that is intended only for the use of the individual(s) and entity(ies) to whom it is addressed. If you are the intended recipient, further disclosures are prohibited
without proper authorization. If you are not the intended recipient, any disclosure, copying, printing, or use of this information is strictly prohibited and possibly a violation of
federal or state law and regulations. If you have received this information in error, please delete it and notify Hamid Khaleghipour at 972-450-2868 immediately. Thank you.
*******************************************************************************************************************