All, ONCOR is on board to meet over at Bella at 10am tomorrow. I need Austin to be there. Anyone else who wants to come is welcome as well. Thanks, Eric From: Eric T. Little Sent: Wednesday, April 06, 2011 10:02 AM To: Todd Henson; 'Christiansen, Eric'; 'Joel Massey'; Barnett, Clay; 'Andrew Harper' Cc: Nick Jacob; Tom Lamberth; Tom Forrest Subject: FW: Vitruvian Park - Power Shut Off Request Gents, We might have a major issue on our hands here. While getting ONCOR set up to shut the power down on Monday for our arch installation, Karen noted that the arches cannot be 10’ or less from the power lines once they are re-energized. Nick and I just went out and put a tape on this and it looks like we are somewhere around 7’ from the outside edge of the east arch to the first power line. I’m trying to set up a meeting tomorrow at 10am with ONCOR onsite to discuss. I will let you know once the meeting is set up. Thanks, Eric From: Karen.Eastman@oncor.com [mailto:Karen.Eastman@oncor.com] Sent: Wednesday, April 06, 2011 9:46 AM To: Eric T. Little Cc: Daniel.Renteria@oncor.com; Johnny.Reames@oncor.com Subject: FW: Vitruvian Pakr - Power Shut Off Request Eric, Construction requests a meeting at the site to discuss. Are you available tomorrow morning at 9:00? Thank You, Karen Eastman New Construction Manager Oncor Electric Delivery 200 North Ector Euless, Texas 76039 Office 817-355-7050 Fax 817-355-7090 From: Reames, Johnny Sent: Wednesday, April 06, 2011 9:20 AM To: Renteria, Daniel Cc: Eastman, Karen Subject: FW: Vitruvian Pakr - Power Shut Off Request Danny, is this the one you took care of last year? If so could you submit a switching order and get with Karen on this. Also I think it would be a good idea to meet with them on sight to make sure of the clearance before they start putting up the arch. Thanks ________________________________ From: Eastman, Karen Sent: Wednesday, April 06, 2011 9:09 AM To: Reames, Johnny Subject: FW: Vitruvian Pakr - Power Shut Off Request Johnny, Please see the note below. A few months ago we installed disconnects in the line on the east side of the Vitruvian Park development so that we could shut down the power so that they could get their equipment in the area of our lines to install the piers for the new bridge. We need to switch the power for the bridge arch installation. I am told that the arch will be no closer than 12 ft to our line. Can we get switching scheduled for Monday the 11th? Please let me know so that I may let the customer know. We will need to verify that our clearance from the arch is adequate. Do we need to meet with the customer prior to Monday morning? Thank You, Karen Eastman New Construction Manager Oncor Electric Delivery 200 North Ector Euless, Texas 76039 Office 817-355-7050 Fax 817-355-7090 From: Eric T. Little [mailto:ELittle@udr.com] Sent: Wednesday, April 06, 2011 8:03 AM To: Eastman, Karen Subject: Vitruvian Pakr - Power Shut Off Request Karen, On Monday, April 11th, we will be erecting the arches on the Bella bridge. As we’ve previously discussed, the arch on the east side of the bridge will be within 10’ of your power line. We will need you guys to come shut down power at the disconnects you installed several months ago. The power will need to be down from 8am till 4pm. See the attached for clarification on the location I am talking about. Please let me know if this will be an issue. Thanks, Eric Confidentiality Notice: This email message, including any attachments, contains or may contain confidential information intended only for the addressee. If you are not an intended recipient of this message, be advised that any reading, dissemination, forwarding, printing, copying or other use of this message or its attachments is strictly prohibited. If you have received this message in error, please notify the sender immediately by reply message and delete this email message and any attachments from your system.