Eric, Yall did say 6-8 weeks, so I took the average. All kidding aside, I did not think it would be helpful to have a meeting on the day we go to bid, so I ended it a week early. Probably should have been more clear in the email, but we can reiterate that at the kickoff meeting. Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857 -----Original Appointment----- From: Christiansen, Eric [mailto:echristiansen@halff.com] Sent: Thursday, March 04, 2010 11:01 AM To: Clay Barnett Subject: Accepted: Vitruvian Park Bridge Design Meeting When: Occurs every Thursday effective 3/18/2010 until 4/22/2010 from 9:30 AM to 10:30 AM Central Standard Time. Where: Svc Ctr - 1st Flr Conf Room Clay, You mention the bridges are going out to bid on April 22, but that's only seven weeks from today. While we'll be delighted to finish sooner if we can, we respectfully request that the bid date be April 29, which is eight weeks away and in accordance with our contract. Thanks, Eric