Bill,
We decided to go with Halff for the inspection of the abutments, bents , rails, decking, etc. However, we do need Kleinfelder to perform the materials testing and to continue to inspect
the drilled shafts. Please send me a work order for this portion of the work in the amount of $90,500.
Thanks,
Clay Barnett, P.E.
Town Engineer
Town of Addison
16801 Westgrove Drive
Addison, TX 75001-2818
Office: (972) 450-2857
From: Bill Campbell [mailto:owcampbell@kleinfelder.com]
Sent: Monday, August 23, 2010 2:09 PM
To: Clay Barnett
Subject: Vitruvian bridges
Good morning. I just wanted to follow up and see what decision had been made on the structural inspections for the bridges. Thanks.
Bill Campbell, Jr., P.E.
N. Texas/Oklahoma Business Unit Leader
2035 Central Circle #110
McKinney, TX 75069
o| 972.562.4677
c| 214.837.4476
f| 972.542.4366
Warning: Information provided via electronic media is not guaranteed against
defects including translation and transmission errors.
If the reader is not the intended recipient, you are hereby notified that any
dissemination, distribution or copying of this communication is strictly
prohibited. If you have received this information in error, please notify the
sender immediately.