Clay, Please find the attached Change Order #2 for Vitruvian Park Public Infrastructure – Phase 1D. Per your request, it has been modified to include the charge for additional steel reinforcement. I have left the cost of the additional waterproofing blank as well as the total amount of CO #2 and the revised contract amount. FYI, the amount of CO #2 is $96,552.63, not including the waterproofing. The only other issue is a request for additional time. While I don't believe additional time would be necessary for waterproofing, I have left this item blank as well. FYI, the total number of days requested for CO #2 is 23, not including time for waterproofing. I will adjust the document as soon as the waterproofing items are sent to my attention. Let me know if you have any problems with the attached file. Eric Eric S. Christiansen, P.E., SECB, LEED AP Senior Structural Engineer HALFF ASSOCIATES, INC. 1201 North Bowser Road Richardson, Texas 75081 Phone 214-346-6284 Fax 214-739-0095 Cell 972-955-2996 www.halff.com