Special comments by author: Here's the punchlist for Bella. Action List for Punch List As of 17-May-2011 12:59 PM CT Vitruvian Infrastructure Phase 1D Bridges 4010 Marsh Lane Addison, Texas 75001 Project Number: 1308D Item # Trade Description 001 - Bella Bridge 001.1 Concrete Repair concrete at light pole bases. Responsibility: Derek Dodson Due Date: 17-May-2011 Attachments: Vit Park - Phase 1D - Bella Prelim Punch (6).jpg, Vit Park - Phase 1D - Bella Prelim Punch (7).jpg 001.2 Concrete Rub out vertical faces of abutments Responsibility: Derek Dodson Due Date: 17-May-2011 Attachments: Vit Park - Phase 1D - Bella Prelim Punch (9).jpg 001.3 Concrete Pour earwalls Responsibility: Derek Dodson Due Date: 17-May-2011 001.4 Concrete Repair bird bath Responsibility: Derek Dodson Due Date: 17-May-2011 Attachments: Vit Park - Phase 1D - Bella Prelim Punch (3).jpg 001.5 Electrical Correctly attach light pole base cover Responsibility: Derek Dodson Due Date: 17-May-2011 Attachments: Vit Park - Phase 1D - Bella Prelim Punch (5).jpg Est. Time: 1.00 Hour(s) To-Date: 0.00 Hour(s) 001.6 General Install Vertical Cable at all Corners Responsibility: Derek Dodson Due Date: 17-May-2011 Attachments: Vit Park - Phase 1D - Bella Prelim Punch (8).jpg 001.7 General Remove all concrete from Pedestrian Rails Responsibility: Derek Dodson Due Date: 17-May-2011 001.8 General Clean all trench drain covers Responsibility: Derek Dodson Due Date: 17-May-2011 001.9 General Cold Galv all cut bolts at 401 rail Responsibility: Derek Dodson Due Date: 17-May-2011 001.10 General Clean up and remove trash Responsibility: Derek Dodson Due Date: 17-May-2011 001.11 General Haul off all unsuitable spoils/conc wash outs Responsibility: Derek Dodson Due Date: 17-May-2011 001.12 General Remove form nails Responsibility: Derek Dodson Due Date: 17-May-2011 Attachments: Vit Park - Phase 1D - Bella Prelim Punch .jpg, Vit Park - Phase 1D - Bella Prelim Punch (1).jpg 001.13 General Trim exp joint Responsibility: Derek Dodson Due Date: 17-May-2011 001.14 General Repair sidewalk damaged by power washer Responsibility: Derek Dodson Due Date: 17-May-2011 001.15 General Remove epoxy from 401 rail Responsibility: Derek Dodson Due Date: 17-May-2011 001.16 General Repair gap at trench drain cover Responsibility: Derek Dodson Due Date: 17-May-2011 Attachments: Vit Park - Phase 1D - Bella Prelim Punch (2).jpg 001.17 General Complete installation of vertical cables Responsibility: Derek Dodson Due Date: 17-May-2011 Attachments: Vit Park - Phase 1D - Bella Prelim Punch (4).jpg 001.18 General Remove and correctly re-install soil at Ret Wall Responsibility: Derek Dodson Due Date: 17-May-2011 Show records by page Close .................................................................................. Copyright (c) 1999-2011, Systemates, Inc. View the User Agreement for legal restrictions and terms of use applicable to this site. Use of this site signifies your agreement to the terms of use specified in the User Agreement. Projectmates - The Capital Project Management Software