Special comments by author: The pre-lim punchlist for Bella is attached. As you complete items, please go into Project Mates and check them off and UDR will verify. Thanks, Eric Action List for Punch List As of 13-May-2011 10:40 AM CT Vitruvian Infrastructure Phase 1D Bridges 4010 Marsh Lane Addison, Texas 75001 Project Number: 1308D Item # Discipline Description 001 - Bella Bridge 001.1 General Remove form nails Responsibility: Derek Dodson Due Date: 17-May-2011 Attachments: Vit Park - Phase 1D - Bella Prelim Punch .jpg, Vit Park - Phase 1D - Bella Prelim Punch (1).jpg 002 - Bella Bridge 002.1 General Trim exp joint Responsibility: Derek Dodson Due Date: 17-May-2011 003 - Bella Bridge 003.1 General Repair sidewalk damaged by power washer Responsibility: Derek Dodson Due Date: 17-May-2011 004 - Bella Bridge 004.1 General Remove epoxy from 401 rail Responsibility: Derek Dodson Due Date: 17-May-2011 005 - Bella Bridge 005.1 General Repair gap at trench drain cover Responsibility: Derek Dodson Due Date: 17-May-2011 Attachments: Vit Park - Phase 1D - Bella Prelim Punch (2).jpg 006 - Bella Bridge 006.1 Concrete Repair bird bath Responsibility: Derek Dodson Due Date: 17-May-2011 Attachments: Vit Park - Phase 1D - Bella Prelim Punch (3).jpg 007 - Bella Bridge 007.1 General Complete installation of vertical cables Responsibility: Derek Dodson Due Date: 17-May-2011 Attachments: Vit Park - Phase 1D - Bella Prelim Punch (4).jpg 008 - Bella Bridge 008.1 General Remove and correctly re-install soil at Ret Wall Responsibility: Derek Dodson Due Date: 17-May-2011 G001 - Bella Bridge G001.1 Electrical Correctly attach light pole base cover Responsibility: Derek Dodson Due Date: 17-May-2011 Attachments: Vit Park - Phase 1D - Bella Prelim Punch (5).jpg Est. Time: 1.00 Hour(s) To-Date: 0.00 Hour(s) G001A - Bella Bridge G001A.1 Concrete Repair concrete at light pole bases Responsibility: Derek Dodson Due Date: 17-May-2011 Attachments: Vit Park - Phase 1D - Bella Prelim Punch (6).jpg, Vit Park - Phase 1D - Bella Prelim Punch (7).jpg G002 - Bella Bridge G002.1 General Install Vertical Cable at all Corners Responsibility: Derek Dodson Due Date: 17-May-2011 Attachments: Vit Park - Phase 1D - Bella Prelim Punch (8).jpg G003 - Bella Bridge G003.1 General Remove all concrete from Pedestrian Rails Responsibility: Derek Dodson Due Date: 17-May-2011 G004 - Bella Bridge G004.1 General Clean all trench drain covers Responsibility: Derek Dodson Due Date: 17-May-2011 G005 - Bella Bridge G005.1 Concrete Rub out vertical faces of abutments Responsibility: Derek Dodson Due Date: 17-May-2011 Attachments: Vit Park - Phase 1D - Bella Prelim Punch (9).jpg G006 - Bella Bridge G006.1 General Cold Galv all cut bolts at 401 rail Responsibility: Derek Dodson Due Date: 17-May-2011 G007 - Bella Bridge G007.1 General Clean up and remove trash Responsibility: Derek Dodson Due Date: 17-May-2011 G008 - Bella Bridge G008.1 General Haul off all unsuitable spoils/conc wash outs Responsibility: Derek Dodson Due Date: 17-May-2011 G009 - Bella Bridge G009.1 Concrete Pour earwalls Responsibility: Derek Dodson Due Date: 17-May-2011 Show records by page Close .................................................................................. Copyright (c) 1999-2011, Systemates, Inc. View the User Agreement for legal restrictions and terms of use applicable to this site. Use of this site signifies your agreement to the terms of use specified in the User Agreement. Projectmates - The Capital Project Management Software