>> Leave comment << Response to RFI No. 59 As of 28-Jan-2011 1:25 PM CT Vitruvian Infrastructure Phase 1D Bridges 4010 Marsh Lane Addison, Texas 75001 Project Number: 1308D Status: Complete Subject HOT! Ponte Ave Bridge Deck Overhang Reinforcing Reason Code None Question Sheet S1-16 states that Z bars are to be spaced 6" in the bottom of the overhang. This is in conflict with the PCP standard on sheet S4-09 that states Z bars are to be spaced 18". Please confirm that the PCP sheet supercedes the Deck Plan sheet. Proposed Solution Attached Files (none) Section: 3 - Concrete Int. Tracking #: Days Elapsed: 0 From: Andrew Harper Originated: 28-Jan-2011 11:41 AM CT To: Eric Christiansen (First Recipient) Requested By: 31-Jan-2011 12:00 AM CT (Original 31-Jan-2011 11:37 AM CT) Copy to: Jonathan McCulley Eric Little Nick Jacob Todd Henson Derek Dodson Additional Info Proposed Solution Impact Critical Path? Yes Cost Change: Yes, may be Time Change: Yes, may be Discipline Code: N/A Drawing Numbers: Needs Drawing Change? N/A History (Chronological Order) No history to display. Final Response (Closing) Response Typcially, job-specific sheets take precedence over standards. However, the 18" spacing that was specified for the Z bars on the PCP standard will be acceptable in this case. Billable n/a Attached Files (none) From: Eric Christiansen Sent: 28-Jan-2011 1:25 PM CT To: Andrew Harper Copy to: Jonathan McCulley Eric Little Nick Jacob Todd Henson Derek Dodson Clay Barnett .................................................................................. Copyright (c) 1999-2011, Systemates, Inc. View the User Agreement for legal restrictions and terms of use applicable to this site. Use of this site signifies your agreement to the terms of use specified in the User Agreement. Projectmates - The Capital Project Management Software