Clay/Jerry: I have attached the plans, pricing form, and specifications for the proposed relocation of the 8” and 12” sanitary sewer force mains that are in conflict with the West Side hole drainage improvements. The current plan is to include these changes into the MALSR change order. If you could review these documents and let me know as soon as possible of any corrections that need to be made that would be great. If you have any questions regarding these changes just let me know. Again thanks for helping us resolve this issue. Thanks, Mitchell McAnally Project Engineer Office: 972-377-7480 Direct: 972-377-7480 E-mail: MRMcAnally@GarverUSA.com