Addison Runway Improvements Project Progress Report September 11, 2009 Work Completed / In-Progress 1. Project Schedule has been revised per Pre-Design Kickoff meeting (1st attachment) 2. RDD supplemental agreement has been signed by Garver and sent to TxDOT for final execution 3. FWD testing was completed Sept. 9th 1. RDD testing should be completed tonight, Sept. 11th 2. TxDOT has revised Airport Development Worksheet to show D-III as (ARC) Airport Reference Code (2nd attachment) 3. Topographic surveys are approximately 50% complete Upcoming Items 1. FWD & RDD test results review meeting with Town, Airport, TxDOT, Garver, Fugro a. Tentatively scheduled for Sept. 21st – TxDOT to confirm availability next week 2. Runway coring to be approximately 3 days after test results review meeting a. Exact date/time to be determined once meeting is scheduled Schedule Project is ahead of schedule Please let me know if you have any comments or questions. Thanks. Frank McIllwain, PE Senior Project Manager Transportation Team Leader Office: 972-377-7480 Ext: 222 Mobile: 214-250-3967 E-mail: FOMcIllwain@GarverUSA.com