Tim,
Did the flood study from Halff provide you with the information you needed or are there additional plans that you need?
Thanks,
Clay Barnett, P.E.
Town Engineer
Town of Addison
16801 Westgrove Drive
Addison, TX 75001-2818
Office: (972) 450-2857
-----Original Message-----
From: Clay Barnett
Sent: Friday, November 13, 2009 2:58 PM
To: 'Siemens, Paul, T'
Cc: Nancy Cline
Subject: RE: Airport Drainage
Tim,
The closest thing we have to a drainage manual is on the Town of Addison website. However, we usually just use Carrollton’s. I will have Dave Wilde see what he can dig up in the way
of plans.
If you need anything else, just let me know.
Thanks,
Clay
-----Original Message-----
From: Siemens, Paul, T [mailto:PTSiemens@GarverUSA.com]
Sent: Friday, November 13, 2009 10:54 AM
To: Nancy Cline
Cc: Clay Barnett
Subject: RE: Airport Drainage
Clay,
Do you have anything on the drainage? Again, if it helps I can send one of our EIT’s down there to dig thru archives.
Nancy,
How about the Drainage Manual?
Thanks.
P. Timothy Siemens, PE
Garver, LLC
From: Siemens, Paul, T
Sent: Monday, November 09, 2009 4:15 PM
To: Nancy S Cline PE (ncline@addisontx.gov)
Cc: Clay Barnett PE (cbarnett@addisontx.gov)
Subject: Airport Drainage
Nancy,
We’ve got a copy of the Town’s Drainage Manual dated March, 1990. Has the manual been updated since then? Or is the 1990 version still current?
Clay,
We talked about as-built’s and drainage maps some time back. Specifically, we’re looking for info on the basin that drains into the Million Air ditch.
Based on what we’ve gathered to date, anything north & east of Westgrove (as far north as Trinity Mills and as far east as Addison Road) would be helpful.
If it helps, I can send one of our EIT’s down to search thru archives. Let me know.
Thanks.
P. Timothy Siemens, PE
Senior Project Manager
Aviation Team Leader
Office: 972-377-7480 Ext: 227
Mobile: 214-938-4291
E-mail: PTSiemens@GarverUSA.com