There is a concrete "cap" over the culvert pipes (see attached). It is approximately 12-18 inches thick on both sides of each pipe, and presumably thicker between the pipes. If this is insufficient, let me know and I will relay that to the contractor. If it is insufficient, they will be required to excavate and remove all the existing concrete, at which point it would be easier to simply remove the entire assembly and relay new pipe and encase it. What do you want me to tell them? David E. Wilde Town of Addison Public Works Inspector 972-450-2847 dwilde@addisontx.gov -----Original Message----- From: Nancy Cline Sent: Tuesday, May 25, 2010 1:00 PM To: Clay Barnett; David Wilde Subject: Exec hangar We are looking at some things with Joe and Frank at the airport. They noticed that the driveway for exec hangar does not look like they plan to concrete encase the culverts under the taxiway. Please ensure that the encasement gets done. Thank you, Nancy.