FYI… Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857 From: Andy Nord [mailto:andy@ntexcon.com] Sent: Monday, February 21, 2011 1:33 PM To: 'Bruce Dunne' Cc: Clay Barnett; 'Zach Fusilier'; 'Josh Hodsdon' Subject: RE: Vitruvian Park - Phase 1E Change Order #1 Bruce We have a few comments on the change order. First off, all of the silt fence has been installed along Vitruvian Way, so Item 2.07 needs to stay at the original quantity of 610 LF. Second, I am attaching a letter from Durable Specialties about how the added work they are to perform will add days to their work. They are saying that they will need an extra 12 days for this work. We realize that some of this work will be occurring concurrently with other work, but would ask for an additional 6 days be added to this change order for a total contract time add of 14 days, when you include our original 8 days for NTC work. Please let me know if you have any questions or would like to discuss any of this. Thanks Andy Andy Nord Cell: 817.819.4117 Email: anord@ntexcon.com From: Bruce Dunne [mailto:bdunne@icon-engineers.com] Sent: Friday, February 18, 2011 9:16 AM To: andy@ntexcon.com Cc: cbarnett@addisontx.gov Subject: Vitruvian Park - Phase 1E Change Order #1 Andy – attached for your review and comment is Change Order #1 for the Vitruvian Park – Phase 1E Extension portion of the Spring Valley Road/Vitruvian Way Reconstruction project. Call if any questions. BRUCE F. DUNNE, P.E. President icon Consulting Engineers, Inc. Bicentennial Financial Center 250 W. Southlake Blvd., Suite 117 Southlake, Texas 76092 Phone: (817) 552-6210 Fax: (817) 552-3126 Mobile: (817) 707-9711