Mike, Thank you for talking to me this morning and I hope we can get a confirmation of the direction we are proceeding this week. We would appreciate it if you could review the attached information about the Vitruvian Way Extension and let us know if AT&T would like to partner as was done on the original portion of Vitruvian Way. The contractor for the project received a Notice to Proceed and started construction today. Previously, AT&T provided the manholes and pipe for the contractor. If there is a different plan, we need to know so we can order the materials for the contractor. The entire road widening project needs to be completed before next August and the opening of the new DISD Elementary School (George H.W. Bush Elementary) at Vitruvian Way and Spring Valley. Please contact me or Clay Barnett as soon as you can. Here is Clay's information, mine is below. Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857 Thank you, Nancy Cline, P.E. Director of Public Works 16801 Westgrove Drive Addison,TX 75001-2818 Office: (972) 450-2878 Cell: (214) 215-5280