Joel,
Please include this with the change order.
The pricing for the five items is attached.
Thanks,
Clay Barnett, P.E.
Town Engineer
Town of Addison
16801 Westgrove Drive
Addison, TX 75001-2818
Office: (972) 450-2857
From: Joel Massey [mailto:jmassey@icon-engineers.com]
Sent: Friday, February 11, 2011 3:33 PM
To: Josh Hodsdon
Cc: Andy Nord; Clay Barnett; Nancy Cline; Romanowski, Mike; Bruce Dunne
Subject: RE: RFI #8
Josh,
The manhole elevation cannot really be adjusted up because of crossing conflicts in Vitruvian Way. This manhole will need to be a drop connection. Per our meeting in the field today,
attached is the exterior drop manhole connection detail. This detail was included in the revised sheets.
Please let me know if you need anything else.
Joel A. Massey
Project Manager
icon Consulting Engineers, Inc.
Bicentennial Financial Center
250 W. Southlake Blvd., Suite 117
Southlake, Texas 76092
Phone: (817) 552-6210
Fax: (817) 552-3126
Mobile: (817) 229-7944
jmassey@icon-engineers.com
From: Josh Hodsdon [mailto:jhodsdon@ntexcon.com]
Sent: Friday, February 11, 2011 8:29 AM
To: Joel Massey
Cc: 'Andy Nord'; 'Clay Barnett'; 'Nancy Cline'; 'Romanowski, Mike'; Bruce Dunne
Subject: RE: RFI #8
Joel,
It looks as though the depth of the manhole will be shallower than originally proposed (5 feet as opposed to 8 feet). We will be exposing the line this morning and I will provide you
with the horizontal as well as vertical information.
Thanks,
Josh Hodsdon
Project Manager
North Texas Contracting, Inc. 4999 Keller Haslet Road Fort Worth, Texas 76248
M: 817.401.1913 O: 817.430.9500 F: 817.719.9440 E: josh@ntexcon.com
From: Joel Massey [mailto:jmassey@icon-engineers.com]
Sent: Friday, February 11, 2011 7:53 AM
To: Josh Hodsdon
Cc: Andy Nord; Clay Barnett; Nancy Cline; Romanowski, Mike; Bruce Dunne
Subject: RE: RFI #8
Josh,
The intent of the “Warning” note was to verify horizontally and vertically where the existing sanitary sewer line was located so that adjustments (east-west, north-south and vertical)
could be made prior to the construction of the manhole in Vitruvian Way and to the east. I recommend that the existing sanitary sewer be located at the existing cleanout first. The
new manhole locations can be shifted as needed. Extending a service lateral to intercept the existing line may add unwanted additional bends in the service line.
Please let me know what you find.
Joel A. Massey
Project Manager
icon Consulting Engineers, Inc.
Bicentennial Financial Center
250 W. Southlake Blvd., Suite 117
Southlake, Texas 76092
Phone: (817) 552-6210
Fax: (817) 552-3126
Mobile: (817) 229-7944
jmassey@icon-engineers.com
From: Josh Hodsdon [mailto:josh@ntexcon.com]
Sent: Thursday, February 10, 2011 4:46 PM
To: 'Nancy Cline'; 'Clay Barnett'; Joel Massey; 'Romanowski, Mike'
Cc: 'Andy Nord'
Subject: RFI #8
All,
Please see RFI #8 attached.
Cheers,
Josh Hodsdon
Project Manager
North Texas Contracting, Inc. 4999 Keller Haslet Road Fort Worth, Texas 76248
M: 817.401.1913 O: 817.430.9500 F: 817.719.9440 E: josh@ntexcon.com