Mike,
1. The roadway needs to be complete by August 2011. I figure 9 months in construction, so we need to start construction in December 2010. With two months to bid it, that places
completed plans on October, 2010. That gives approximately 3-4 months for design.
2. Yes, streetscape will be required.
3. Icon is realigning Vitruvian Way. There will be some coordination for the intersection.
4. I believe that is in Icon’s contract. We can verify prior to requesting a proposal.
5. Signal upgrade will be included in this contract.
If you have any other questions, please let me know.
Thanks,
Clay Barnett, P.E.
Town Engineer
Town of Addison
16801 Westgrove Drive
Addison, TX 75001-2818
Office: (972) 450-2857
From: Romanowski, Mike [mailto:mromanowski@halff.com]
Sent: Thursday, April 29, 2010 3:03 PM
To: Clay Barnett
Subject: RE: Spring Valley
Clay,
Just a few more questions and I should be good to go.
1. When do you need the project finished?
2. Is landscaping/irrigation/ other streetscape required?
3. Are you wanting the skew to come out of the intersection?
4. ROW/prepare parcels for widening/ intersection realignment included?
5. If intersection is realigned, then signal upgrade also included?
Just want to make sure we have the right people on the org chart to take care of what's needed.
Not trying to make the project bigger than it needs to be, but I recall this intersection is tight.
________________________________
From: Clay Barnett [mailto:cbarnett@addisontx.gov]
Sent: Thursday, April 29, 2010 2:44 PM
To: Romanowski, Mike
Subject: RE: Spring Valley
Mike,
Attached is the RFQ.
The relocation of Brookhaven Club Drive will be done by Icon. The design of Spring Valley and the intersection will be by the engineer selected from the RFQ.
If you have any additional questions, please let me know.
Thanks,
Clay Barnett, P.E.
Town Engineer
Town of Addison
16801 Westgrove Drive
Addison, TX 75001-2818
Office: (972) 450-2857
From: Romanowski, Mike [mailto:mromanowski@halff.com]
Sent: Thursday, April 29, 2010 2:12 PM
To: Clay Barnett
Subject: Spring Valley
Clay,
One question I had after looking at aerial, will the project include re-configuring the intersection at Vitruvian Way?