Clay, Just a few more questions and I should be good to go. 1. When do you need the project finished? 2. Is landscaping/irrigation/ other streetscape required? 3. Are you wanting the skew to come out of the intersection? 4. ROW/prepare parcels for widening/ intersection realignment included? 5. If intersection is realigned, then signal upgrade also included? Just want to make sure we have the right people on the org chart to take care of what's needed. Not trying to make the project bigger than it needs to be, but I recall this intersection is tight. ________________________________ From: Clay Barnett [mailto:cbarnett@addisontx.gov] Sent: Thursday, April 29, 2010 2:44 PM To: Romanowski, Mike Subject: RE: Spring Valley Mike, Attached is the RFQ. The relocation of Brookhaven Club Drive will be done by Icon. The design of Spring Valley and the intersection will be by the engineer selected from the RFQ. If you have any additional questions, please let me know. Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857 From: Romanowski, Mike [mailto:mromanowski@halff.com] Sent: Thursday, April 29, 2010 2:12 PM To: Clay Barnett Subject: Spring Valley Clay, One question I had after looking at aerial, will the project include re-configuring the intersection at Vitruvian Way? Mike Romanowski, PE Vice President HALFF ASSOCIATES, INC. 1201 North Bowser Road Richardson, Texas 75081 Phone 214-346-6270 Fax 214-739-0095 www.halff.com