Sounds good. I will get right on it. From: Clay Barnett [mailto:cbarnett@addisontx.gov] Sent: Tuesday, January 25, 2011 4:10 PM To: Bruce Dunne Subject: RE: Vitruvian Way Extension - Drawing Revisions 1 Bruce, Please put together a change order for Phase 1E. We will likely keep the change orders for the two separate jobs separate as well just to keep it simple. If you have any questions, please let me know. Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857 From: Bruce Dunne [mailto:bdunne@icon-engineers.com] Sent: Monday, January 24, 2011 1:56 PM To: Clay Barnett Subject: FW: Vitruvian Way Extension - Drawing Revisions 1 We sent our revisions onto Halff as you requested for preparation of a Change Order to add the parallel parking, etc. along Phase 1E-Vitruvian Way. Mike sent the following response that YOU would be preparing the Change Order and circulating the revised drawings to the contractor! How’s that coming???? From: Romanowski, Mike [mailto:mromanowski@halff.com] Sent: Friday, January 21, 2011 12:03 PM To: Joel Massey Subject: RE: Vitruvian Way Extension - Drawing Revisions 1 This is fine Joel, Clay is handling things for Addison as far as changes, etc. I believe he will also be the one to approve and circulate revised drawings to the contractor. From: Joel Massey [mailto:jmassey@icon-engineers.com] Sent: Friday, January 21, 2011 9:45 AM To: Romanowski, Mike Cc: Cline, Nancy S.; Barnett, Clay; Eric T. Little; Bruce Dunne Subject: Vitruvian Way Extension - Drawing Revisions 1 Mike, We have drawing revisions for the Vitruvian Way Extension project being constructed in conjunction with the Spring Valley Road project. I am unclear as to the established construction management procedures for this project, so I am forwarding to you, attached (2 emails), the eleven (11) revised sheets in PDF format, the updated CAD files in MicroStation and AutoCAD formats and the quantity revision tabulation in PDF format. Please let me know if you have any questions or need any additional information. If we should follow some other procedure, please let us know. Joel A. Massey Project Manager icon Consulting Engineers, Inc. Bicentennial Financial Center 250 W. Southlake Blvd., Suite 117 Southlake, Texas 76092 Phone: (817) 552-6210 Fax: (817) 552-3126 Mobile: (817) 229-7944 jmassey@icon-engineers.com ****************************************************************************************************************** This e-mail and any files or attachments transmitted with it contains Information that is confidential and privileged. This document may contain Protected Health Information (PHI) or other information that is intended only for the use of the individual(s) and entity(ies) to whom it is addressed. If you are the intended recipient, further disclosures are prohibited without proper authorization. If you are not the intended recipient, any disclosure, copying, printing, or use of this information is strictly prohibited and possibly a violation of federal or state law and regulations. If you have received this information in error, please delete it and notify Hamid Khaleghipour at 972-450-2868 immediately. Thank you. *******************************************************************************************************************