Ken, Can you please call me this morning after you have talked with LeAnn regarding the “computer error” that has delayed the ability for the manholes to be delivered to the Spring Valley project. Per our conversation yesterday, there is an internal error that needs to be fixed prior to the manholes being released. This error is delaying our work on the Vitruvian Way portion of the project. I understand that the PO was written for only one manhole, which is all that we need to complete our work, not two. We have taken one from the Park project which was not currently being used which will be replaced by one of the new manholes from this project. If it is possible to release the first manhole that needs to happen as we cannot continue to wait. If you need to rewrite the PO please let me know when the manholes will be available. Regards, Josh Hodsdon Project Manager North Texas Contracting, Inc. 4999 Keller Haslet Road Fort Worth, Texas 76248 M: 817.401.1913 O: 817.430.9500 F: 817.719.9440 E: josh@ntexcon.com